Plan Linear cycles using velocity analytics. Suggests scope based on historical capacity, identifies dependency risks, balances workload.
Scanned 9/6/2026
Install to Claude Code
npx -y skills add joa23/linear-cli --skill cycle-plan --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Cycle Plan?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/joa23-cycle-plan-linear-cli)More formats (shields.io, HTML) on the badges page.
---
name: cycle-plan
description: Plan Linear cycles using velocity analytics. Suggests scope based on historical capacity, identifies dependency risks, balances workload.
---
# Cycle Plan Skill - Sprint Planning
You are an expert at planning software development cycles based on team velocity.
## When to Use
Use this skill when:
- Planning the next sprint/cycle
- Deciding what to include in a cycle
- Balancing workload across team members
## Process
1. **Analyze Historical Velocity**
```bash
linear cycles analyze --team ENG --count 5
```
2. **Review Available Capacity**
- Check team size
- Account for PTO/holidays
- Consider focus time needs
3. **Select Issues for Cycle**
- Start with P1/P2 issues
- Respect dependencies
- Balance across team members
4. **Validate Plan**
- Total estimates <= capacity
- No cross-cycle blockers
- Even distribution
## Velocity Analysis
The `linear cycles analyze` command provides:
```
VELOCITY ANALYSIS: Team ENG (5 cycles)
════════════════════════════════════════
Average Velocity: 34 points/cycle
Completion Rate: 85%
Scope Creep: 12%
CYCLE HISTORY
────────────────────────────────────────
Cycle 23: 38 pts (92% complete)
Cycle 22: 32 pts (88% complete)
Cycle 21: 35 pts (82% complete)
Cycle 20: 28 pts (78% complete)
Cycle 19: 37 pts (90% complete)
RECOMMENDATION
────────────────────────────────────────
Target: 32-36 points for next cycle
Buffer: Reserve 10% for unplanned work
```
## Planning Output
```
CYCLE PLAN: Sprint 24
════════════════════════════════════════
Capacity: 40 points (4 engineers)
Target: 36 points (90% capacity)
Buffer: 4 points for unplanned work
PLANNED ISSUES
────────────────────────────────────────
ENG-201 [P1] Auth refactor 8pts @alice
ENG-202 [P1] Payment fix 5pts @bob
ENG-203 [P2] Dashboard update 8pts @carol
ENG-204 [P2] API optimization 5pts @dave
ENG-205 [P3] Docs update 3pts @alice
ENG-206 [P3] Test coverage 5pts @bob
────────────────────────────────────────
Total: 34 points
WORKLOAD BALANCE
────────────────────────────────────────
@alice: 11 pts (28%)
@bob: 10 pts (25%)
@carol: 8 pts (20%)
@dave: 5 pts (13%)
Unassigned: 0 pts
DEPENDENCY RISKS
────────────────────────────────────────
ENG-203 blocked by ENG-201 (same cycle - OK)
```
## Commands Used
```bash
# Analyze velocity
linear cycles analyze --team ENG --count 5
# List upcoming issues
linear issues list --team ENG
# Check dependencies
linear deps --team ENG
# Assign to cycle
linear issues update ENG-201 --cycle current
linear issues update ENG-202 --cycle next
```
## Best Practices
1. **Leave buffer** - Plan to 80-90% capacity
2. **Front-load blockers** - Schedule blocking issues early
3. **Balance workload** - Distribute evenly across team
4. **Avoid cross-cycle deps** - Don't plan work blocked by next cycle