>- Advanced Product Quality Planning (APQP) — plan and track a new product launch through all 5 phases, identify deliverables per phase, run gate reviews, and ensure quality outputs are complete before Start of Production (SOP). Use when launching a new part, managing an APQP project, or auditing APQP completeness. Covers AIAG APQP 2nd edition and IATF 16949 §8.3.
Scanned 9/12/2026
Install to Claude Code
npx -y skills add thedixitjain/the-mega-skill-library --skill apqp --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Apqp?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/thedixitjain-apqp)More formats (shields.io, HTML) on the badges page.
---
name: apqp
description: ">- Advanced Product Quality Planning (APQP) — plan and track a new product launch through all 5 phases, identify deliverables per phase, run gate reviews, and ensure quality outputs are complete before Start of Production (SOP). Use when launching a new part, managing an APQP project, or auditing APQP completeness. Covers AIAG APQP 2nd edition and IATF 16949 §8.3."
category: engineering-core
source_repo: hashgraph-online/awesome-codex-plugins
source_path: "plugins/RBraga01/Quality-Engineering-Skills/skills/planning/apqp/SKILL.md"
source_url: https://github.com/hashgraph-online/awesome-codex-plugins/blob/HEAD/plugins/RBraga01/Quality-Engineering-Skills/skills/planning/apqp/SKILL.md
---
# Advanced Product Quality Planning (APQP)
## When to use
Use this skill when:
- A new product or part is being launched and a structured quality plan is needed
- Managing an APQP project and tracking deliverables across phases
- Conducting an APQP gate review to assess launch readiness
- A customer requests an APQP status report or phase completion confirmation
- Auditing whether a supplier's APQP process is adequate
## Prerequisites
- Customer requirements, specifications, and drawings (or RFQ package)
- Programme timing (SOP date, PPAP submission date, prototype gates)
- Nominated APQP team (cross-functional: engineering, quality, purchasing, manufacturing, logistics)
- Customer APQP template if OEM-specific format required
## Workflow
### Overview — The 5 APQP Phases
```
Phase 1 Phase 2 Phase 3 Phase 4 Phase 5
Plan & Define → Product Design → Process Design → Product & Process → Feedback &
& Development & Development Validation Corrective Action
↓ ↓ ↓ ↓ ↓
Program Prototype Pre-launch PPAP SOP +
approval build build submission Production
```
All phases run with concurrent engineering — phases overlap and teams work in parallel.
---
### Phase 1 — Plan and Define Program
**Objective:** Understand customer requirements and define what the product must do.
**Key deliverables:**
| Deliverable | Description |
|-------------|-------------|
| Voice of the Customer (VOC) | Customer wants, needs, expectations — translated to measurable requirements |
| Design Goals | Product performance targets derived from VOC |
| Reliability and Quality Goals | Target failure rate, warranty targets, Cpk targets |
| Preliminary Bill of Materials | Draft BOM from design intent |
| Preliminary Process Flow | High-level process sequence |
| Preliminary Special Characteristics | Initial list of critical/significant characteristics |
| Product Assurance Plan | Quality plan for the programme |
| Management Support | Signed-off programme charter with resources and timing |
**Gate 1 pass criteria:**
- Customer requirements documented and agreed
- Feasibility confirmed (technical and commercial)
- Team chartered and timing plan approved
- Special characteristics list preliminary but complete
---
### Phase 2 — Product Design and Development
**Objective:** Translate customer requirements into a product design with verified characteristics.
**Key deliverables:**
| Deliverable | Description |
|-------------|-------------|
| DFMEA | Design FMEA — all failure modes analysed, H-AP items addressed |
| Design Verification Plan (DVP) | Test plan linked to DFMEA failure modes |
| Drawing and Specification Release | Fully released engineering drawings and 3D data |
| Material Specifications | Raw material specs, supplier approval plan |
| Drawing and Specification Changes | Change management process in place |
| New Equipment and Tooling | List of new equipment/tooling required |
| Special Product and Process Characteristics | Updated with design detail |
| Gauge Plan | MSA requirement list — which characteristics need MSA studies |
| Prototype Control Plan | Control plan for prototype builds |
| Prototype Build | Prototype parts manufactured and tested |
| Engineering Drawings | Released and approved |
**Gate 2 pass criteria:**
- DFMEA complete with all H-AP actions closed
- DVP complete and test execution started
- Prototype build results acceptable
- All special characteristics identified and confirmed
- No outstanding major design concerns
---
### Phase 3 — Process Design and Development
**Objective:** Design and verify the manufacturing process.
**Key deliverables:**
| Deliverable | Description |
|-------------|-------------|
| Packaging Standards | Packaging design, labelling, MMOG/LE if required |
| Product/Process Quality System Review | Internal quality system audit against customer requirements |
| Process Flow Chart | Detailed process flow for all operations |
| Floor Plan Layout | Manufacturing floor layout approved |
| Characteristics Matrix | Matrix linking process steps to product characteristics |
| PFMEA | Process FMEA — all failure modes, AP ratings, H-AP actions complete |
| Pre-Launch Control Plan | Control plan for pre-launch production |
| Process Instructions | Work instructions for all operations |
| MSA Plan | Gauge R&R plan for all measurement systems |
| Preliminary Process Capability Study Plan | Plan for capability studies on special characteristics |
| Packaging Specifications | Final packaging specs including OEM labelling |
**Gate 3 pass criteria:**
- PFMEA complete, H-AP actions closed or formally accepted
- Pre-launch Control Plan approved
- Process instructions complete for all operations
- Tooling and equipment installed and qualified
- No unresolved open issues blocking pre-launch build
---
### Phase 4 — Product and Process Validation
**Objective:** Validate the production process and prepare for PPAP submission.
**Key deliverables:**
| Deliverable | Description |
|-------------|-------------|
| Production Trial Run | Significant Production Run (minimum run to PPAP requirements) |
| MSA Studies | Gauge R&R completed for all special characteristics |
| Preliminary Process Capability | Cpk study on special characteristics (target ≥ 1.67) |
| Production Part Approval (PPAP) | All 18 PPAP elements complete and submitted |
| Production Validation Testing | Final validation tests on production parts |
| Packaging Evaluation | Production packaging validated |
| Production Control Plan | Final production control plan approved |
| Quality Planning Sign-Off | Customer approval of PPAP and APQP completion |
| Management Support Sign-Off | Internal management approval for SOP |
**Gate 4 pass criteria (= PPAP approval):**
- Significant production run completed (minimum 300 consecutive parts per AIAG PPAP 4th ed §4.0, unless the customer specifies otherwise in writing)
- Dimensional results 100% conforming
- Cpk ≥ 1.67 on all special characteristics (or customer-approved deviation)
- %GRR < 30% for all MSA studies
- PPAP submitted and customer approval received
- No open concerns from validation testing
---
### Phase 5 — Feedback, Assessment and Corrective Action
**Objective:** Continuous improvement after SOP — close the loop on any issues found in production.
**Key activities:**
| Activity | Description |
|----------|-------------|
| Reduced variation | Monitor process capability, reduce common-cause variation |
| Improved customer satisfaction | Track warranty, field returns, and customer scorecards |
| Improved delivery and service | Monitor OTD (on-time delivery) and logistics performance |
| Lessons learned | Document lessons learned for future programmes |
| Control Plan updates | Update based on production data and any quality escapes |
| PFMEA updates | Update based on field failures and warranty data |
**Phase 5 is ongoing.** There is no defined end gate — it runs for the life of the programme.
---
### APQP timing — rule of thumb
| Milestone | Typical timing before SOP |
|-----------|--------------------------|
| Programme approval / Phase 1 complete | 18–24 months |
| Design release / Phase 2 complete | 12–15 months |
| Process design complete / Phase 3 complete | 8–10 months |
| PPAP submission | 4–6 months |
| PPAP approval (customer) | 3–4 months |
| Pre-production builds | 2–3 months |
| SOP | 0 |
Automotive OEM programmes vary — always confirm with the customer's APQP coordinator.
## Validation criteria
At each gate review, verify:
- All deliverables for the phase are complete (not "in progress")
- No open H-AP items in DFMEA or PFMEA without approved actions
- No outstanding design or process concerns without a documented resolution plan
- Team sign-off obtained from all functions (quality, engineering, manufacturing, purchasing)
- Customer confirmation received before advancing to next phase
Gate reviews are STOP gates — do not advance until all criteria are met.
## Common mistakes
- Starting Phase 2 before customer requirements are fully understood and documented (Phase 1 incomplete)
- PFMEA created after process is already running — it must drive process design, not document it
- Production trial run shorter than 300 consecutive parts without written customer authorisation — the PPAP samples must come from this run; a shorter run requires an explicit customer waiver
- Capability studies run on off-tool or pre-production parts — must be from production tooling
- Prototype Control Plan used for PPAP submission — production control plan must be separate
- MSA studies done after PPAP submission — must be complete before PSW is signed
- Phase 5 never started — APQP is treated as "done" at SOP rather than as a continuous loop
- Lessons learned not captured — same problems recur on next programme
## Output Format
At the start of each use, ask the user:
> "How would you like to receive the output?
> **A** — Structured Markdown (formatted tables and sections, ready to copy)
> **B** — Plain tables (simplified structure for Excel or Word)
> **C** — Narrative report (flowing text for a formal document or email)
>
> Default: A."
Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.
## Changelog
| Version | Date | Author | Change |
|---------|------|--------|--------|
| 1.0 | 2026-06-06 | @RBraga01 | Initial release |
| 1.1 | 2026-06-06 | @migmcc | Added 300-part production trial run minimum to Gate 4 criteria and Common Mistakes |
---
**Source:** [`hashgraph-online/awesome-codex-plugins`](https://github.com/hashgraph-online/awesome-codex-plugins) → `plugins/RBraga01/Quality-Engineering-Skills/skills/planning/apqp/SKILL.md`
Is this your skill, or is something wrong with this listing? Request removal or report an issue. Author removals are honored within 72 hours.
No comments yet. Be the first to comment!