Premortem

ASecurity

Use for pre-mortem analysis of decisions, projects, or initiatives—solo or facilitated with a team before a launch or strategic commitment. Trigger when the user says "what could go wrong", "risk assessment", "pre-mortem this", "let's run a pre-mortem", or when evaluating risks for a plan. Three-category framework (Critical, Perceived, Undiscussed risks); team sessions end in an action plan with owners.

  • 7 stars
  • 0 votes
  • 0 copies
  • 4 views
  • Added September 22, 2026
toolsgo

Security analysis

A100/100

Scanned September 22, 2026

npx -y skills add shrwnsan/vibekit-claude-plugins --skill premortem --agent claude-code

Installs into .claude/skills of the current project.

Are you the author of Premortem?

Add the live security badge to your README. It updates with every re-scan.

Security grade badge for Premortem
[![Security: A — Skills Directory](https://www.skillsdirectory.com/api/skills/shrwnsan-premortem/badge)](https://www.skillsdirectory.com/skills/shrwnsan-premortem)

More formats (shields.io, HTML) on the badges page. Keep it an A: scan every change in CI with Pro.

Download with Pro
SKILL.md
---
name: premortem
description: Use for pre-mortem analysis of decisions, projects, or initiatives—solo or facilitated with a team before a launch or strategic commitment. Trigger when the user says "what could go wrong", "risk assessment", "pre-mortem this", "let's run a pre-mortem", or when evaluating risks for a plan. Three-category framework (Critical, Perceived, Undiscussed risks); team sessions end in an action plan with owners.
---

# Premortem

A pre-mortem is prospective hindsight: imagine the project or decision has failed, then work backward to why. Developed by Gary Klein and popularized by Shreyas Doshi, it surfaces risks optimism bias hides.

## When to apply this

Trigger for:
- Major product launches or feature releases
- Strategic initiatives with significant investment
- AI feature deployments (high uncertainty)
- Team reorganizations or process changes
- Any decision worth documenting in a decision log

Skip for: trivially reversible choices, daily execution decisions, routine maintenance.

Before starting, read whatever already exists — project brief, PRD, strategy doc, launch plan. Don't make the user re-explain what's documented.

## The framework

### Step 1: The prompt

Ask yourself: **"If this initiative failed, what would have caused it?"**

Don't just think about it — write down at least 5 reasons.

### Step 2: Categorize the risks

| Category | What it means | How to use it |
|----------|---------------|---------------|
| **🎯 Critical Risks** | Concrete threats causing real damage if unaddressed | Require action items |
| **🔍 Perceived Risks** | Threats others may worry about; you're confident they won't materialize | Document to reassure stakeholders |
| **🔇 Undiscussed Risks** | Important concerns the team isn't openly addressing | Must be surfaced in team contexts |

### Step 3: Assess likelihood and impact

Rate each Critical and Undiscussed risk:

- **Impact**: 1 (minor) to 5 (catastrophic)
- **Likelihood**: 10% to 90% (avoid 0% or 100% certainty)

Priority score = Impact × Likelihood

### Step 4: Brainstorm mitigations

For top 3-5 risks, ask:
- **Prevent**: What would stop this from happening?
- **Detect**: How would we know early if it's starting?
- **Recover**: If it happens, how do we limit damage?

### Step 5: Decide what to accept

Not everything needs mitigation. Explicitly list what you're accepting, with rationale: "We're accepting X because Y, and will monitor Z indicator."

## Facilitating a team pre-mortem

For a group session, add the facilitation layer:

1. **Set the frame out loud first.** The psychology flips: instead of avoiding problems to be supportive, the group actively seeks problems to be helpful. State it: *we're imagining failure to prevent it, not to criticize* — everyone gets credit for identifying real risks.
2. **Pose the prompt vividly:** "Imagine this project failed spectacularly six months from now — what went wrong?"
3. **Quiet brainstorm before discussion.** 5–10 minutes of silent writing, then go around the room — stops the loudest voice anchoring the list.
4. **Use the Undiscussed category deliberately.** Creates permission to flag what the team is too polite to raise.
5. **End in an action plan, not a mood.** Every top risk gets a mitigation with a **single owner** (not "the team"), a **deadline**, and **success criteria**. A pre-mortem ending in a brainstorm with no owners is anxiety, not a pre-mortem.

Red flags to name in the room: too few Critical risks (safety problem or overconfidence), all Perceived and no Critical (avoiding real concerns), zero Undiscussed risks (the team isn't comfortable yet), everything rated maximum impact (force-rank).

## Pre-mortem for AI features

Add these AI-specific failure modes:

- **Hallucination risk**: confident-looking but wrong output
- **Refusal/over-refusal**: valid inputs rejected or too conservative
- **Prompt injection**: malicious inputs overriding behavior
- **Data leakage**: sensitive information exposed in responses
- **Cost explosion**: usage spikes beyond budget

## Pre-mortem checklist

- [ ] At least 5 failure modes identified
- [ ] Critical Risks have proposed mitigations
- [ ] Top risks have owners/timelines
- [ ] Accepted risks are intentional, not accidental
- [ ] Early warning indicators defined

## Output

Produce a concise risk register:

```markdown
# Pre-mortem: [Initiative Name]

## Critical Risks
| Risk | Impact | Likelihood | Mitigation | Owner |
|------|--------|------------|------------|-------|
| [risk] | [1-5] | [%] | [action] | [name] |

## Undiscussed Risks to Surface
- [concern the team may not be addressing]

## Early Warning Indicators
- [metric or signal to watch]

## Accepted Risks
- [what we're not mitigating and why]
```

## Integration points

- **`demo-prep`**: Feed pre-mortem risks into Pass 3
- **`decision-log`**: Capture pre-mortem insights for AI decisions tied to model versions
- **`prioritization-frameworks`**: Use likelihood scores in WSJF or Cost of Delay calculations

## Anti-patterns to avoid

- **False precision**: Don't rate likelihood as 73% when you mean "likely"
- **Everything is critical**: If all risks are 5-impact, force-rank them
- **No Undiscussed Risks in team settings**: A comfortable team surfaces unspoken concerns
- **Analysis paralysis**: More than 7 Critical Risks means over-analysis or poor scoping

Attribution

Is this your skill, or is something wrong with this listing? Request removal or report an issue. Author removals are honored within 72 hours.

Comments

Loading comments…

Newsletter

Get the weekly list of safe new skills, and the ones we pulled.