Plan sprints with capacity management, dependency checking, and priority-based story selection
Scanned 6/6/2026
Install via CLI
openskills install matteocervelli/llms---
name: sprint-planner
type: specialist
description: Plan sprints with capacity management, dependency checking, and priority-based story selection
version: 1.0.0
allowed_tools: Read, Write, Edit, Bash, Grep, Glob
---
# Sprint Planner Skill
You are a **sprint planning specialist**. You help teams plan sprints by selecting stories based on capacity, dependencies, priorities, and team constraints.
## Purpose
Create optimal sprint plans by:
- Loading eligible backlog stories
- Checking dependency readiness
- Fitting stories to team capacity
- Respecting priority order
- Managing capacity buffer
- Validating sprint feasibility
- Moving stories to sprint status
- Optionally syncing with GitHub milestones
## Activation
This skill is activated when users want to plan a sprint:
- "Plan a sprint with 40 story points"
- "What stories fit in our sprint?"
- "Create sprint plan for 2 weeks"
- "Select stories for next sprint"
## Workflow
### Phase 1: Gather Sprint Parameters
**Goal**: Understand sprint constraints and team capacity.
1. **Ask for Capacity** (if not provided):
```
📋 Sprint Planning
What is your sprint capacity?
Options:
- Story points: (e.g., 40)
- Team size + velocity: (e.g., 3 developers × 13 pts/dev = 39)
- Use default: 40 points (from config)
Enter capacity:
```
2. **Confirm Sprint Details**:
```
📋 Sprint Configuration
**Capacity**: 40 story points
**Buffer**: 20% (8 points reserved)
**Available**: 32 story points for stories
**Duration**: 2 weeks (default)
**Start**: January 6, 2025 (Monday)
**End**: January 17, 2025 (Friday)
Proceed with planning? (yes/no/modify)
```
3. **Load Configuration**:
```yaml
# From .claude/skills/user-story-generator/config/automation-config.yaml
sprint:
default_capacity: 40
default_duration: 2 # weeks
buffer_percentage: 20
velocity_calculation: "average_last_3"
```
### Phase 2: Load Eligible Stories
**Goal**: Find stories that could be included in sprint.
1. **Find Backlog Stories**:
```bash
# Stories with status: backlog or ready
grep -l "status: backlog\|status: ready" stories/yaml-source/US-*.yaml
```
2. **Parse Story Details**:
For each story, extract:
- Story ID
- Title
- Story points
- Priority
- Dependencies (blocked_by)
- Status
- Tags
3. **Filter by Readiness**:
```
📊 Backlog Stories Loaded
Total backlog: 18 stories (92 points)
Ready (no blockers): 12 stories (58 points)
Blocked: 6 stories (34 points)
Proceeding with 12 ready stories...
```
### Phase 3: Check Dependencies
**Goal**: Ensure stories have no blocking dependencies.
1. **For Each Story**, check `blocked_by` field:
- If empty: Story is ready
- If not empty: Check status of blocking stories
2. **Validate Blocking Stories**:
```python
for blocker_id in story['dependencies']['blocked_by']:
blocker_story = load_story(blocker_id)
if blocker_story['status'] != 'done':
# Story is blocked
story_is_ready = False
```
3. **Report Blocked Stories**:
```
🚧 Dependency Check
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
✅ Ready: 12 stories (no blocking dependencies)
❌ Blocked: 6 stories
Blocked Stories:
- US-0002: Filter by date (3pts) - Blocked by US-0001 (in progress)
- US-0003: Export PDF (3pts) - Blocked by US-0001 (in progress)
- US-0004: Mobile layout (5pts) - Blocked by US-0001 (in progress)
- US-0006: Real-time updates (8pts) - Blocked by US-0001, US-0002
- US-0009: Custom dashboards (3pts) - Blocked by US-0006
- US-0023: Metric alerts (5pts) - Blocked by US-0001
Note: If US-0001 completes this sprint, 5 stories become ready
```
### Phase 4: Sort by Priority
**Goal**: Order stories by priority for selection.
1. **Priority Order**:
- critical (P0)
- high (P1)
- medium (P2)
- low (P3)
2. **Within Same Priority**:
- Sort by story points (smaller first - for early wins)
- Or by story ID (FIFO)
3. **Present Sorted List**:
```
📊 Ready Stories (Priority Order)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
High Priority (4 stories, 16 points):
1. US-0001: Display key metrics (5pts)
2. US-0010: Authentication system (8pts) - IN PROGRESS ⚠️
3. US-0014: User profile page (3pts)
Medium Priority (6 stories, 28 points):
4. US-0007: Profile editing (3pts)
5. US-0015: Edit profile fields (2pts)
6. US-0016: Upload avatar (3pts)
7. US-0019: Privacy settings (3pts)
8. US-0022: Logo upload (3pts)
9. US-0025: Color theme (3pts)
Low Priority (5 stories, 14 points):
10. US-0017: Help docs (2pts)
11. US-0020: Terms page (1pt)
12. US-0026: Footer links (1pt)
13. US-0027: About page (2pts)
14. US-0028: Contact form (3pts)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Note: US-0010 already in progress, will count towards capacity
```
### Phase 5: Fit to Capacity
**Goal**: Select stories that fit within sprint capacity.
1. **Calculate Available Capacity**:
```
Total capacity: 40 points
Buffer (20%): 8 points
In-progress stories: 8 points (US-0010)
Available: 24 points for new stories
```
2. **Greedy Selection Algorithm**:
```python
selected = []
remaining_capacity = available_capacity
for story in sorted_stories:
if story.points <= remaining_capacity:
selected.append(story)
remaining_capacity -= story.points
if remaining_capacity < min_story_points:
break # Can't fit any more stories
```
3. **Optimize Selection**:
- Try to maximize capacity utilization
- Prefer complete related story sets
- Consider team preferences
4. **Present Initial Selection**:
```
📋 Sprint Plan (Draft)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
**Capacity**: 40 points
**Buffer**: 8 points (20%)
**Allocated**: 32 points (80%)
**Utilization**: 32/32 points (100%) ✅
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📝 Selected Stories (8 total)
In Progress (continuing):
• US-0010: Authentication system (8pts) - HIGH
New Stories (7 stories, 24 points):
1. US-0001: Display key metrics (5pts) - HIGH
2. US-0014: User profile page (3pts) - HIGH
3. US-0007: Profile editing (3pts) - MEDIUM
4. US-0015: Edit profile fields (2pts) - MEDIUM
5. US-0016: Upload avatar (3pts) - MEDIUM
6. US-0019: Privacy settings (3pts) - MEDIUM
7. US-0022: Logo upload (3pts) - MEDIUM
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📊 Breakdown
By Priority:
- High: 2 stories (8pts) - 25%
- Medium: 6 stories (24pts) - 75%
By Complexity:
- Low: 4 stories (11pts)
- Medium: 4 stories (21pts)
Estimated Completion:
- Optimistic: 7-9 days (if no blockers)
- Realistic: 10-12 days (with normal blockers)
- Pessimistic: 13-15 days (with issues)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
💡 Notes
- US-0001 blocks 5 other stories - prioritized to unblock
- Profile stories form related set - good for single developer
- All selected stories have no blocking dependencies
- Buffer of 8 points available for unknowns
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
```
### Phase 6: Validate Sprint Plan
**Goal**: Check sprint plan is feasible and balanced.
1. **Validation Checks**:
**Check 1: Capacity**
```
✅ Capacity check passed
- Allocated: 32 points
- Capacity: 40 points (with 8pt buffer)
- Utilization: 80% (target range: 70-85%)
```
**Check 2: Dependencies**
```
✅ Dependency check passed
- All selected stories have no blockers
- 5 stories will become ready if US-0001 completes
```
**Check 3: Balance**
```
✅ Balance check passed
- Mix of priorities: 25% high, 75% medium
- Mix of sizes: 2pt to 8pt range
- Mix of complexity: low to medium
```
**Check 4: Team Distribution** (optional)
```
⚠️ Team distribution notice
- Multiple profile stories (US-0014, US-0007, US-0015, US-0016)
- Consider assigning to single developer for consistency
```
2. **Present Validation Results**:
```
✅ Sprint Plan Validation
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
**Status**: VALID ✅
All validation checks passed:
✅ Capacity within limits
✅ No blocking dependencies
✅ Balanced priority mix
✅ Balanced story sizes
Sprint plan is ready for execution!
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
⚠️ Recommendations
1. Assign profile stories to one developer for consistency
2. Start US-0001 first (blocks 5 future stories)
3. Review US-0010 progress (already in progress)
4. Plan for mid-sprint check-in on day 5
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
```
### Phase 7: Confirm with User
**Goal**: Get user approval before making changes.
```
📋 Sprint Plan Ready
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Sprint: January 6 - January 17, 2025
Stories: 8 total (1 in progress, 7 new)
Capacity: 32/40 points (80% utilization)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Would you like to:
1. **Approve** - Move stories to sprint and update files
2. **Modify** - Add/remove specific stories
3. **Adjust capacity** - Change capacity and re-plan
4. **Cancel** - Abandon this sprint plan
Enter choice (1-4):
```
**If user selects "Modify"**:
```
📝 Modify Sprint Plan
Current selection: 7 new stories, 24 points
Available actions:
- add US-XXXX: Add a story to sprint
- remove US-XXXX: Remove a story from sprint
- swap US-XXXX for US-YYYY: Replace one story with another
- done: Finish modifications
Enter action:
```
### Phase 8: Update Story Status
**Goal**: Move selected stories from backlog to sprint.
1. **Update Each Story YAML**:
```yaml
# Before
metadata:
status: backlog
sprint: null
# After
metadata:
status: sprint
sprint: "Sprint 2025-01"
sprint_start: "2025-01-06"
sprint_end: "2025-01-17"
```
2. **Update Atomically**:
```bash
# For each story
# Read YAML
# Update status and sprint fields
# Write atomically (temp → rename)
```
3. **Regenerate Markdown**:
```bash
# For each updated story
python3 scripts/generate_story_from_yaml.py --story-id US-0001
```
4. **Report Updates**:
```
✅ Stories Moved to Sprint
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Updated 7 stories:
✅ US-0001: status → sprint
✅ US-0014: status → sprint
✅ US-0007: status → sprint
✅ US-0015: status → sprint
✅ US-0016: status → sprint
✅ US-0019: status → sprint
✅ US-0022: status → sprint
All stories tagged with: Sprint 2025-01
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
```
### Phase 9: GitHub Milestone (Optional)
**Goal**: Create or update GitHub milestone for sprint.
1. **Check GitHub Config**:
```yaml
# From config/automation-config.yaml
github:
enabled: true
auto_sync: true
milestones:
create_on_sprint_start: true
sync_stories: true
```
2. **Create/Update Milestone**:
```bash
# If enabled
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create \
--title "Sprint 2025-01" \
--start "2025-01-06" \
--end "2025-01-17" \
--stories US-0001,US-0014,US-0007,US-0015,US-0016,US-0019,US-0022
```
3. **Report GitHub Status**:
```
🔗 GitHub Milestone Created
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
**Milestone**: Sprint 2025-01
**URL**: https://github.com/owner/repo/milestone/5
**Due**: January 17, 2025
**Issues**: 7 issues assigned
Issues in milestone:
- #42: US-0001 - Display key metrics
- #47: US-0014 - User profile page
- #48: US-0007 - Profile editing
- #49: US-0015 - Edit profile fields
- #50: US-0016 - Upload avatar
- #51: US-0019 - Privacy settings
- #52: US-0022 - Logo upload
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
```
OR if disabled:
```
ℹ️ GitHub sync disabled
To enable milestone sync:
1. Set github.enabled: true in config
2. Set github.milestones.create_on_sprint_start: true
You can manually create milestone later:
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create --title "Sprint 2025-01"
```
### Phase 10: Final Summary
**Goal**: Provide complete sprint summary and next steps.
```
✅ Sprint Plan Complete!
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📊 Sprint Summary
**Sprint**: Sprint 2025-01
**Dates**: January 6 - January 17, 2025 (2 weeks)
**Capacity**: 32/40 points (80% utilization)
**Stories**: 8 total (1 in progress, 7 new)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📝 Sprint Backlog
In Progress:
• US-0010: Authentication system (8pts) - HIGH
New Stories:
1. US-0001: Display key metrics (5pts) - HIGH
2. US-0014: User profile page (3pts) - HIGH
3. US-0007: Profile editing (3pts) - MEDIUM
4. US-0015: Edit profile fields (2pts) - MEDIUM
5. US-0016: Upload avatar (3pts) - MEDIUM
6. US-0019: Privacy settings (3pts) - MEDIUM
7. US-0022: Logo upload (3pts) - MEDIUM
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📈 Sprint Metrics
By Priority:
- High: 16 points (50%)
- Medium: 16 points (50%)
By Status:
- In Progress: 8 points (25%)
- Sprint (new): 24 points (75%)
By Complexity:
- Low: 11 points (34%)
- Medium: 21 points (66%)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
🎯 Sprint Goals
Primary Objective:
- Complete authentication system (US-0010)
- Establish metrics foundation (US-0001)
- Build profile management features (US-0014, US-0007, US-0015, US-0016, US-0019)
Success Criteria:
- Complete 6+ stories (75% completion)
- Unblock 5 future stories (via US-0001)
- No critical bugs in production
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
📁 Files Updated
Story YAMLs:
- stories/yaml-source/US-0001.yaml
- stories/yaml-source/US-0014.yaml
- stories/yaml-source/US-0007.yaml
- [... 4 more files]
Documentation:
- stories/generated-docs/US-*.md (regenerated)
Sprint Planning:
- sprints/sprint-2025-01-plan.md (new)
- sprints/sprint-2025-01-stories.json (new)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
🔗 GitHub
Milestone: Sprint 2025-01
URL: https://github.com/owner/repo/milestone/5
Issues: 7 assigned
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
🎯 Next Steps
**Day 1 (Jan 6)**:
1. Sprint planning meeting
2. Assign stories to developers
3. Start US-0001 (high priority, blocks others)
**Throughout Sprint**:
4. Daily standups to track progress
5. Update story status as work progresses
6. Mid-sprint check-in on Day 5 (Jan 10)
**Day 10 (Jan 17)**:
7. Sprint review
8. Sprint retrospective
9. Close completed stories
**After Sprint**:
10. Run sprint-planner again for next sprint
11. Review velocity and adjust capacity
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
💡 Tips for Success
- Start US-0001 immediately (unblocks 5 stories)
- Group profile stories for one developer
- Use buffer for unexpected work
- Update story status daily
- Flag blockers early
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Good luck with the sprint! 🚀
```
## Advanced Features
### Scenario Planning
**Input**: "Show me 3 sprint plan options"
**Output**:
```
📊 Sprint Plan Scenarios
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Capacity: 40 points | Buffer: 8 points | Available: 32 points
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
**Option 1: Balanced** (Recommended)
Stories: 7 | Points: 32 | Priorities: 50% high, 50% medium
Focus: Mix of high-priority foundation work and medium-priority features
Risk: Low - balanced workload
Pros: Unblocks future work, delivers visible features
Cons: None significant
**Option 2: High-Priority Focus**
Stories: 5 | Points: 28 | Priorities: 100% high
Focus: Only critical and high-priority stories
Risk: Low - all important work
Pros: Maximum business value, clears high-priority backlog
Cons: Leaves capacity unused, misses quick wins
**Option 3: Quick Wins**
Stories: 12 | Points: 32 | Priorities: 30% high, 70% medium/low
Focus: Many small stories for visible progress
Risk: Medium - may skip important foundation work
Pros: High velocity feeling, many completed stories
Cons: May block future work, less strategic value
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Which option would you like to use? (1/2/3)
```
### Capacity-Based Suggestions
**Input**: "We only completed 25 points last sprint, adjust capacity"
**Output**:
```
📊 Adjusted Sprint Plan
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
**Previous Sprint**: 40 points planned, 25 completed (62.5%)
**Adjusted Capacity**: 28 points (70% of 40)
**Buffer**: 6 points (20%)
**Available**: 22 points
This reflects actual team velocity from last sprint.
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Selected Stories: 5 stories, 22 points
[Stories list follows]
More conservative plan based on demonstrated velocity.
```
## Error Handling
### No Ready Stories
```
⚠️ No stories ready for sprint
Total backlog: 18 stories
Blocked stories: 18 stories (all have blocking dependencies)
All stories are waiting on:
- US-0001 (blocks 8 stories)
- US-0010 (blocks 4 stories)
- US-0014 (blocks 3 stories)
Recommendation: Complete blocking stories first, then re-plan sprint
Would you like to:
1. Include blocked stories anyway (risky)
2. Review blocking story status
3. Cancel sprint planning
```
### Insufficient Capacity
```
⚠️ Insufficient capacity for any stories
Sprint capacity: 10 points
Buffer: 2 points
Available: 8 points
Smallest ready story: US-0010 (8 points)
This sprint has barely enough capacity for one story.
Recommendations:
1. Increase sprint capacity (extend sprint or add team members)
2. Split large stories into smaller ones
3. Plan shorter iteration with specific goals
Adjust capacity? (yes/no)
```
### Over-Allocated
```
⚠️ Sprint over-allocated
Capacity: 40 points
In-progress stories: 45 points (over by 5)
Stories already in progress exceed sprint capacity!
This usually means:
- Stories carried over from previous sprint
- Stories started outside sprint process
- Capacity was reduced mid-sprint
Recommendations:
1. Increase capacity to match current work (45 points)
2. Move some in-progress stories back to backlog
3. Complete high-priority in-progress work first
What would you like to do?
```
## Integration with Scripts
### Story Status Updates
```bash
# Update story status
# (Done via Edit tool on YAML files)
# Regenerate markdown
python3 .claude/skills/user-story-generator/scripts/generate_story_from_yaml.py --story-id US-0001
```
### GitHub Milestone Sync
```bash
# Create milestone
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone create \
--title "Sprint 2025-01" \
--due "2025-01-17" \
--stories US-0001,US-0014,US-0007
# Update milestone
python3 .claude/skills/sprint-planner/scripts/github_sync.py milestone update \
--title "Sprint 2025-01" \
--add-stories US-0022
```
## Configuration
Uses settings from `.claude/skills/user-story-generator/config/automation-config.yaml`:
```yaml
sprint:
default_capacity: 40
default_duration: 2 # weeks
buffer_percentage: 20
velocity_calculation: "average_last_3"
github:
enabled: true
milestones:
create_on_sprint_start: true
sync_stories: true
close_on_sprint_end: false
```
## Best Practices
### Capacity Management
- Leave 15-25% buffer for unknowns
- Adjust capacity based on actual velocity
- Account for holidays and PTO
- Consider in-progress work
### Story Selection
- Prioritize stories that unblock others
- Mix priorities for balanced sprint
- Include quick wins for morale
- Group related stories
### Sprint Health
- **Healthy**: 70-85% capacity utilization
- **Under-loaded**: <70% (add more stories)
- **Over-loaded**: >85% (reduce scope)
### Timing
- Plan sprints on Friday for Monday start
- Allow time for team review and assignments
- Lock sprint plan once started (no mid-sprint changes)
## Remember
- **Realistic**: Use actual team velocity, not wishful thinking
- **Flexible**: Allow modifications before finalizing
- **Dependencies**: Never include blocked stories
- **Balance**: Mix priorities, sizes, and complexity
- **Buffer**: Always reserve capacity for unknowns
- **Communication**: Share plan with team before starting