Generate Closure Report

ASecurity

Generates a project closure report aggregating data from charter, plan-fact report, risk register, and lessons learned. Last artifact of the Closing phase. Summarizes project outcomes, deviations, realized risks, and lessons.

  • 18 stars
  • 0 votes
  • 0 copies
  • 1 view
  • Added May 27, 2026
data-aigotesting

Works with

  • cli

Security analysis

A100/100

Pro scans all 5 files and shows the line behind each finding

Scanned September 6, 2026

npx -y skills add KirKruglov/claude-skills-kit --skill generate-closure-report --agent claude-code

Installs into .claude/skills of the current project.

Are you the author of Generate Closure Report?

Add the live security badge to your README. It updates with every re-scan.

Security grade badge for Generate Closure Report
[![Security: A — Skills Directory](https://www.skillsdirectory.com/api/skills/kirkruglov-generate-closure-report/badge)](https://www.skillsdirectory.com/skills/kirkruglov-generate-closure-report)

More formats (shields.io, HTML) on the badges page. Keep it an A: scan every change in CI with Pro.

Download with Pro
SKILL.md
---
name: generate-closure-report
description: >
  Generates a project closure report aggregating data from charter, plan-fact
  report, risk register, and lessons learned. Last artifact of the Closing phase.
  Summarizes project outcomes, deviations, realized risks, and lessons.
template: closure-report
output_file: closure-report.md
phase: "6 — Closing"
version: 1.0.0
---

# generate-closure-report

## Triggers

**Russian:** «сформируй отчёт о закрытии», «закрой проект», «подготовь closure report», «отчёт о закрытии проекта»
**English:** "generate closure report", "close project", "project closure report", "prepare closure report"

## Language Detection

Determine the language of the user's request:
- If the request is in Russian → use templates with `-ru` suffix
- Otherwise → use templates with `-en` suffix

All output (headings, labels, comments, instructions) must match the detected language.

---

## 1. Input Data

| Data | Required | Source | Notes |
|------|:--------:|--------|-------|
| Project charter | yes | knowledge (`project-charter.md`) | Goal, deliverables, team, sponsor, budget, timeline |
| Plan-fact report | yes | knowledge (`plan-fact-report.md`) | Deviation summary, actual dates/budget/scope. If multiple files — use the latest by date |
| Lessons learned | yes | chat | User provides in any format: retrospective results, questionnaire answers, free text. Agent structures and assigns categories |
| Risk register | no | knowledge (`risk-register.md`) | For section 4. If unavailable — agent asks the user about realized risks |
| Open items | no | chat | Tasks/questions remaining after closure. If not provided — replace section with "All items closed" |
| Lessons source | no | chat | `team retrospective` / `questionnaire` / `PM input in chat`. Default: `PM input in chat` |

If required data is missing — request it (system-prompt-draft.md §3.2):

```
To generate the project closure report, the following is needed:
1. Project charter (project-charter.md) — in knowledge or paste in chat.
2. Plan-fact report (plan-fact-report.md) — in knowledge or paste in chat.
3. Project lessons — in any format:
   — team retrospective results;
   — questionnaire answers;
   — free-form description: what went well, what went wrong, what to do differently.
Available data: [list what is present].
Missing: [specify].
```

---

## 2. Execution Algorithm

1. **Verify input data.** Check for minimum: charter, plan-fact report, lessons from user. Missing → request using the template from §1. Do NOT generate a stub report, template, or example — respond ONLY with a data request. Present → step 2.
2. **Structure lessons.** If data is free-form — categorize into: Processes, Technologies, Communications, Resources, Risks. For each lesson — formulate a recommendation. Count: 1 to 5, only those supported by data. Do not pad artificially.
3. **Check data for contradictions.** If charter data conflicts with plan-fact report (e.g., different planned dates or budget) — do NOT choose independently. List the discrepancies, ask which data is current. Exception: if the user explicitly corrects in chat — use the correction.
4. **Read the template** `closure-report` from project knowledge. Select the file with the appropriate language suffix based on Language Detection.
5. **Fill section 1** (general information): planned data from charter, actual data from plan-fact report (summary).
6. **Fill section 2** (project results): list of deliverables from charter (section 2, "Project Result"). Actual status from plan-fact report (scope data) or from user. Split into "Delivered" / "Not delivered / deferred". For each incomplete deliverable — state the reason. If reason not provided — use `[clarify]`.
7. **Fill section 3** (plan-fact deviations): copy the summary table from plan-fact-report.md (section 1). Data: plan, actual, deviation — without recalculation. Rephrase the "Comment" column in a closing tone (1 sentence per metric). At the bottom — reference: "Details — in `plan-fact-report.md`."
8. **Fill section 4** (realized risks):
   - If `risk-register.md` is available → extract risks with status "realized" or mentioned in user data. Verify: each risk in section 4 must have an ID from the register.
   - If `risk-register.md` is unavailable → use data from user. If user did not specify realized risks — ask: "Which planned risks were realized? If none — I will note 'No realized risks'."
   - If no risks occurred → replace the table with: "No realized risks".
9. **Fill section 5** (lessons learned): 1 to 5 lessons, structured in step 2. Category from the reference in §3.
10. **Fill section 6** (open items) and section 7 (closure approval):
    - Section 6: if user provided open items → fill in. If not → replace the table with: "All items closed".
    - Section 7: names from charter (Sponsor, PM). Dates — empty.
11. **Verify the result** against the checklist (section 5 of this spec). Present the result in chat. Format (system-prompt-draft.md §3.4):
    - What was done: "Generated project closure report based on [list sources]".
    - Assumptions: list all (if any).
    - Key outcomes: 1–3 lines — main results (delivered X of Y, budget, timeline).
    - Required: "Approve, provide comments, or reject".
    - Do not show system file paths. Use name only: "Report saved as closure-report.md".
12. **Wait for user response** (system-prompt-draft.md §3.5).
    - Approval → produce the final text.
    - Comments → revise, show updated version. After the 3rd iteration — ask: "Continue revising or finalize the current version?"
    - **After approval:**
      - Offer the user text to insert into log.md and project-state.md (system-prompt-draft.md §11).
      - State: "Closure report approved. Project completed." This is the final skill in the MVP chain — no subsequent tasks.

---

## 3. Section Fill Rules

### Section 1. General Information

- Project goal — from charter (section 1). Copy as-is, do not rephrase.
- Sponsor — from charter (section 5 or header).
- Start and end dates (planned) — from charter (section 3).
- End date (actual) — from plan-fact report (last actual date) or from user. If project closes early — state the actual date with a note.
- Budget (planned) — from charter (section 4). Budget (actual) — from plan-fact report (summary).

### Section 2. Project Results

- **Delivered:** each deliverable from charter (section 2, "Included") that is complete. Format: `deliverable — brief result description`.
- **Not delivered / deferred:** deliverables that are incomplete or deferred. Format: `deliverable — reason: [explanation]`. If reason not provided by user — `[clarify]`.
- Status source: plan-fact report (scope data) > user data in chat.
- If a deliverable is partially complete — list under "Delivered" with a "partial" note and description of what was excluded.

### Section 3. Plan-Fact Deviations

- **Direct transfer** of the summary table from plan-fact-report.md (section 1, 3 rows: timeline, budget, scope). Do not recalculate data.
- "Comment" column — rephrase from plan-fact report in a closing tone. One sentence per metric. Example: "Delay +1 week due to Safari hotfix" → "Project completed with a +1 week delay; root cause — Safari incident during launch phase".
- If budget was absent in plan-fact report — replace the budget row with "Budget — data unavailable".
- Below the table — in italics: *Details — in `plan-fact-report.md`.*

### Section 4. Realized Risks

**Conditional section.**

- If risks were realized — table with columns: ID, Risk, Project Impact, Response Result.
- **ID** — from risk-register.md (if available). If register unavailable — leave empty or assign R1, R2, ...
- **Project Impact** — specific: what happened, what consequences (delay, overrun, scope change).
- **Response Result** — what was done: did the response plan work, what actions were taken.
- If no risks occurred → replace the table with: "No realized risks".
- Do not include risks that were in the register but did not materialize.

### Section 5. Lessons Learned

- 1 to 5 lessons. Count is determined by user data — do not pad artificially.
- Columns: #, Lesson, Category, Recommendation.
- **Category** — from reference: `Processes` / `Technologies` / `Communications` / `Resources` / `Risks`.
- **Lesson** — a fact or observation. Wording: what happened and why it matters.
- **Recommendation** — a concrete action for future projects. Not an abstraction.
- If user provided lessons without categories — agent assigns based on content.

### Section 6. Open Items and Handover

**Conditional section.**

- If open items exist — table: #, Item/Task, Owner, Deadline.
- Owner — from user data. If not specified — `[clarify]`.
- Deadline — specific date (YYYY-MM-DD). If not specified — `[clarify]`.
- If no open items → replace the table with: "All items closed".

### Section 7. Closure Approval

- Sponsor and PM — from charter (section 5). Date — empty (filled upon approval).

### Header Metadata

- `Version`: 1.0
- `Date`: current generation date.
- `File`: `closure-report.md`
- `Document status`: `draft` (on generation). After approval — `approved`.
- `Project manager`: from charter.
- `Lessons source`: from input data. Default: `PM input in chat`.

---

## 4. Placeholder Table

> Placeholders `{{}}` in the template are fill guides, not auto-substitution variables. Replace each with the corresponding value from input data.

| Placeholder | Required | Source | Allowed Values |
|-------------|:--------:|--------|----------------|
| `{{project_name}}` | yes | charter | text |
| `{{date}}` | yes | system | YYYY-MM-DD |
| `{{pm_name}}` | yes | charter | name |
| `{{lessons_source}}` | yes | chat (default: `PM input in chat`) | `team retrospective` / `questionnaire` / `PM input in chat` |
| `{{project_goal}}` | yes | charter (section 1) | text |
| `{{sponsor_name}}` | yes | charter | name |
| `{{planned_start}}` | yes | charter (section 3) | YYYY-MM-DD |
| `{{planned_end}}` | yes | charter (section 3) | YYYY-MM-DD |
| `{{actual_end}}` | yes | plan-fact report / chat | YYYY-MM-DD |
| `{{planned_budget}}` | no | charter (section 4) | number + currency |
| `{{actual_budget}}` | no | plan-fact report | number + currency |
| `{{deliverable_N}}` | yes (≥1) | charter (section 2) | deliverable name |
| `{{status_N}}` | yes | plan-fact report / chat | brief result description |
| `{{excluded_N}}` | no | charter / plan-fact report | undelivered deliverable name |
| `{{reason_N}}` | no | chat / plan-fact report | reason or `[clarify]` |
| `{{planned_duration}}` | yes | plan-fact report (summary) | number + unit |
| `{{actual_duration}}` | yes | plan-fact report (summary) | number + unit |
| `{{delta_time}}` | yes | plan-fact report (summary) | text (e.g., "+1 week (+8%)") |
| `{{comment_time}}` | yes | agent (based on plan-fact report) | closing comment, 1 sentence |
| `{{delta_budget}}` | no | plan-fact report (summary) | text (e.g., "-$3,600 (-4.5%)") |
| `{{comment_budget}}` | no | agent (based on plan-fact report) | closing comment, 1 sentence |
| `{{planned_scope}}` | yes | plan-fact report (summary) | number + unit (deliverables) |
| `{{actual_scope}}` | yes | plan-fact report (summary) | number + unit |
| `{{delta_scope}}` | yes | plan-fact report (summary) | text (e.g., "-1 deliverable") |
| `{{comment_scope}}` | yes | agent (based on plan-fact report) | closing comment, 1 sentence |
| `{{risk_id}}` | no | risk-register / agent | ID (e.g., R001) or empty |
| `{{risk_description}}` | no | risk-register / chat | risk description |
| `{{impact}}` | no | chat / agent | specific project impact |
| `{{response_result}}` | no | chat / agent | response result |
| `{{lesson_N}}` | yes (≥1) | chat (structured by agent) | text — fact/observation |
| `{{category_N}}` | yes | agent | `Processes` / `Technologies` / `Communications` / `Resources` / `Risks` |
| `{{recommendation_N}}` | yes | agent | concrete action |
| `{{open_item_N}}` | no | chat | question or task |
| `{{owner_N}}` | no | chat | owner or `[clarify]` |
| `{{deadline_N}}` | no | chat | YYYY-MM-DD or `[clarify]` |

---

## 5. Validation Checklist

Before presenting the result to the user — verify:

- [ ] All required placeholders replaced with values
- [ ] No `{{}}` placeholders remain in text (except removed optional rows)
- [ ] Section 1: planned data matches charter, actual data matches plan-fact report
- [ ] Section 2: all deliverables from charter listed (delivered + undelivered)
- [ ] Section 2: each undelivered deliverable has a reason (or `[clarify]`)
- [ ] Section 3: data matches plan-fact report summary (no recalculation)
- [ ] Section 3: reference to `plan-fact-report.md` present
- [ ] Section 4: if conditional — correctly filled or replaced with "No realized risks"
- [ ] Section 5: 1 to 5 lessons, each with category and recommendation
- [ ] Section 6: if conditional — correctly filled or replaced with "All items closed"
- [ ] All agent assumptions listed when presenting result
- [ ] Document status = `draft`
- [ ] File: `closure-report.md` stated in header

---

## 6. Dependencies

**Consumes (input):**
- `project-charter.md` — from skill `generate-charter` (goal, deliverables, team, budget, timeline)
- `plan-fact-report.md` — from skill `generate-plan-fact-report` (deviation summary, actual data)
- `risk-register.md` — from skill `generate-risk-register` (optional, for realized risks)
- Lessons and open items — from user (via chat)

**Produces (output):** project closure report — the final artifact. Not consumed by other MVP skills.

In Product 1: additionally consumes data from `generate-questionnaire` (team lessons via questionnaire).

After report approval, user should upload `closure-report.md` to project knowledge for archival.

---

## 7. Example Invocation

**User command:**

> Generate the project closure report. Charter and plan-fact report are in knowledge. Risk register too.
> Lessons:
> — Underestimated DB filter complexity, lost a week. Need to budget buffer for unknown tasks.
> — Formalized change request saved us from scope creep — CEO wanted to add Intercom, but impact assessment stopped it.
> — Safari testing was done only before release — needs to happen earlier.
> Open items:
> — Email integration assigned to Dmitry, deadline July 31.
> — Pricing — on me, by August 1.

**Agent response (after generation):**

> Generated project closure report for "ClientBoard" based on: charter, plan-fact report, risk register, lessons from chat.
>
> Assumptions:
> - Lessons source: PM input in chat.
> - Realized risks identified based on risk-register.md and PM data.
>
> Key outcomes:
> - Delivered 4 of 5 deliverables (email integration deferred).
> - Budget: $76,400 of $80,000 (4.5% savings).
> - Timeline: +1 week (13 instead of 12).
>
> Required: approve, provide comments, or reject.
>
> [report text]

---

## Changelog

| Date | Version | Change |
|------|---------|--------|
| 2026-03-26 | 1.0 | Skill created. Aggregation from charter + plan-fact report + lessons. Conditional sections 4/6. 1 to 5 lessons |

Files in this skill

  • README.md2 KB
  • README.ru.md3.2 KB
  • SKILL.md15 KB
  • templates/closure-report-en.md2.4 KB
  • templates/closure-report-ru.md3.4 KB

Attribution

Is this your skill, or is something wrong with this listing? Request removal or report an issue. Author removals are honored within 72 hours.

Comments

Loading comments…

Newsletter

Get the weekly list of safe new skills, and the ones we pulled.