description: Generate project status report for leadership in RAG format
---
# Status Report
Generate a project status report for "$ARGUMENTS" in RAG format (Red/Amber/Green) suitable for leadership review. Summarize progress against milestones, highlight risks and issues, note upcoming milestones, and list asks from leadership.
## Prerequisites
None — this is a utility skill. It can be run at any time, with or without existing project artifacts.
If `.project/$ARGUMENTS/` exists, read any available artifacts for context. If it does not exist, proceed based on information the user provides.
## Process
1. **Read existing context:**
- If `.project/$ARGUMENTS/` exists, read all available artifacts for comprehensive context:
- Project charter, roadmap, and backlog for planned scope and milestones
- Sprint data for recent progress and velocity
- Risk assessments for known risks
- Decision logs for recent decisions
- Previous status reports for trend comparison
- If no artifacts exist, gather the information from the user through targeted questions
2. **Set overall RAG status with justification:**
- **Green — on track:** project is progressing as planned, no significant risks or blockers, timeline confidence is high
- **Amber — challenges but manageable:** some risks or issues exist but have mitigation plans, timeline may slip slightly, needs monitoring
- **Red — blocked or at-risk:** significant blockers or risks threatening delivery, timeline is at serious risk, needs leadership attention or intervention
- Provide a one-line justification for the status: "Green: delivering on schedule with all milestones met this period"
- If the status has changed from the previous report, explain why
- Be honest — do not default to Green to avoid difficult conversations
3. **Summarize progress against milestones:**
- For each milestone or major deliverable:
- **Status** — completed, in progress, not started, at risk, blocked
- **% complete** — estimated progress
- **Key accomplishments this period** — what was delivered or achieved since last report
- Highlight any milestones that slipped and explain why
- Note velocity trends: is the team accelerating, maintaining, or slowing down?
4. **List top 3 risks and issues:**
- Distinguish between risks (potential problems) and issues (current problems)
- For each:
- **Description** — what is the risk or issue
- **Impact** — what happens if it materializes or is not resolved
- **Mitigation** — what is being done about it
- **Owner** — who is responsible for managing it
- Limit to top 3 — leadership does not need an exhaustive list, they need the critical items
- If there are more than 3, note "N additional risks tracked in the risk register"
5. **Note upcoming milestones and timeline confidence:**
- List the next 2-3 milestones with target dates
- For each, state confidence level: high (>80% likely on time), medium (50-80%), low (<50%)
- If any milestone is at medium or low confidence, briefly explain why
- Note any dependencies on external teams, vendors, or decisions
6. **List asks and decisions needed from leadership:**
- Be specific: "We need approval for X by [date]" or "We need a decision on Y to unblock Z"
- For each ask, explain: what is needed, why, by when, and what happens if it is delayed
- Limit to 2-3 actionable asks — this is the most important section for leadership
- If there are no asks, explicitly state "No asks this period"
7. **Include team capacity note:**
- Is the team fully staffed or are there gaps?
- Note any planned or unplanned absences that affect delivery
- Flag if the team is at capacity and new work cannot be absorbed without deprioritizing something
- Note upcoming capacity changes (new hires, departures, leaves)
8. **Write the artifact** — save to `.project/$ARGUMENTS/status-report.md`:
- **Report Date** — date of this report
- **Overall Status** — RAG indicator with one-line justification
- **Progress Summary** — milestone status with % complete and key accomplishments
- **Risks & Issues** — top 3 with impact, mitigation, and owner
- **Upcoming Milestones** — next 2-3 milestones with dates and confidence levels
- **Asks from Leadership** — specific requests with deadlines
- **Team Capacity** — staffing and availability notes
- **Trend** — comparison with previous report status if available
## Output
Status report saved to `.project/$ARGUMENTS/status-report.md`. Present a summary highlighting:
- Overall RAG status with justification
- Key accomplishment this period
- Top risk or issue requiring attention
- Most urgent ask from leadership (if any)