Use when prepare fracture-control inputs for a safety or project review milestone under ECSS-E-ST-32C §5.3: determine which FCI list maturity level is required for each milestone (SRR through AR), verify that all required fracture-control deliverables are present before the review gate, confirm that open action items from previous reviews are closed, and check that the fracture control plan, fracture analysis, and NDE procedures meet the required completeness for the milestone. Trigger: ecss,...
Scanned 9/27/2026
Install to Claude Code
npx -y skills add ashfordeOU/aero-agent-skills --skill fracture-control-reviews --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Fracture Control Reviews?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/ashfordeou-fracture-control-reviews)More formats (shields.io, HTML) on the badges page.
---
name: fracture-control-reviews
description: "Use when prepare fracture-control inputs for a safety or project review milestone under ECSS-E-ST-32C §5.3: determine which FCI list maturity level is required for each milestone (SRR through AR), verify that all required fracture-control deliverables are present before the review gate, confirm that open action items from previous reviews are closed, and check that the fracture control plan, fracture analysis, and NDE procedures meet the required completeness for the milestone. Trigger: ecss, e-st-32-structures-scope, fracture-control-reviews, fci-list, project-reviews, safety-reviews, review-readiness, nde, action-items."
license: Apache-2.0
compliance: STANDARDS-REF
standards:
- id: ecss
reference-only: true
gated: false
domain: space-systems
pack: space-systems
compatibility: "agentskills.io SKILL.md; any SKILL.md host (Claude Code, Hermes, OpenClaw)"
metadata:
domain: space-systems
subdomain: ecss
tags: [ecss, e-st-32-structures-scope, fracture-control-reviews, fci-list, project-reviews, safety-reviews, review-readiness, nde]
version: 0.1.0
author: Aero Agent Skills
---
# ECSS Structures — Fracture-Control Inputs to Safety and Project Reviews (space-systems/ecss/fracture-control-reviews)
Use when the task is preparing and verifying the fracture-control inputs
that must be submitted at each safety and project review milestone under
ECSS-E-ST-32C §5.3 — from the System Requirements Review (SRR) through
the Acceptance Review (AR).
## Domain quick reference
- ECSS-E-ST-32C §5.3 requires that fracture-control information be
provided at each project review milestone. The exact set of required
deliverables scales with design maturity: early reviews accept
preliminary outputs, while later reviews demand final, verified, or
accepted products. Submitting an under-mature deliverable — e.g. a
draft FCI list at CDR instead of a final list — is a gate-failure
finding.
- The Fracture-Critical Item (FCI) list is the central tracking document.
Its maturity progresses through five levels: preliminary (SRR), draft
(PDR), final (CDR), verified (QR), and accepted (AR). At each
milestone the submitted FCI list must meet or exceed the level required
for that gate.
- Required deliverables per milestone:
- **SRR**: draft fracture control plan, preliminary FCI list, draft
fracture criteria.
- **PDR**: baselined fracture control plan, draft FCI list, preliminary
fracture analysis, baselined fracture criteria.
- **CDR**: approved fracture control plan, final FCI list, final
fracture analysis, draft NDE procedures, fracture test plan, and
closure of all CDR-predecessor action items.
- **QR**: verified FCI list, final fracture analysis, NDE results,
fracture test results, test-analysis correlation, closure of prior
action items.
- **AR**: accepted FCI list, fracture summary report, NDE acceptance
records, dispositioned waivers, closure of prior action items.
- Open action items from a previous review must be formally closed before
the current review gate can be passed. An unresolved action item is a
blocking finding.
## Workflow
1. Identify the target review milestone (SRR, PDR, CDR, QR, or AR) and
retrieve the required fracture-control input set for that milestone.
Reject any milestone identifier not in the standard sequence.
2. Determine the FCI list maturity level required for the milestone.
Compare it against the maturity level of the FCI list currently
available. If the available level is below the required level, flag a
maturity shortfall and identify how many maturity steps are needed.
3. For each required deliverable in the milestone input set, confirm
whether it is available. Record present and missing items separately.
4. If the milestone is CDR or later, confirm that the item
`previous_review_actions_closed` is in the available set. An absent
closure record is an automatic blocking finding regardless of other
deliverable status.
5. Determine review readiness: the gate passes only when every required
deliverable is present (missing set is empty) and the FCI list maturity
meets the requirement. Any shortfall produces a non-ready result with
an explicit list of gaps.
6. Report the readiness verdict, the list of missing inputs, the FCI
maturity comparison, and the index of the milestone in the
SRR→PDR→CDR→QR→AR sequence so that predecessor and successor
milestones can be identified.
## Pitfalls
- Submitting a deliverable that exists but at an insufficient maturity
level and counting it as present — the maturity check is separate from
the presence check; a draft FCI list does not satisfy the CDR
requirement for a final FCI list.
- Treating a missing fracture control plan as acceptable at early
milestones because no analysis exists yet — even at SRR a draft plan
is required to establish the programme framework.
- Carrying an open action item from a previous review into the current
review gate without a formal closure record — the standard requires
closure before the gate, not at the gate.
- Using a single pass/fail flag without recording which specific inputs
are missing — the review board needs an itemised gap list to assign
responsible engineers and set closure dates.
## Behavior contract (gate 3)
The milestone required-inputs, FCI maturity, readiness-check, and
action-item closure logic is exercised by the gate 3 contract test:
scripts/test_fracture_control_reviews.py against
scripts/fracture_control_reviews_logic.py (stdlib unittest, offline). Run:
python3 scripts/test_fracture_control_reviews.py
## Compliance
- ECSS standards are freely downloadable (ESA); cite the source and
paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.