Use when defining verification stages for a product under ECSS-E-ST-10-02C: qualify, accept, verify pre-launch, in-orbit (incl. commissioning) and post-landing each with its objective and applicability to the product's launched/recovered life profile, ahead of stage-specific planning (qualification, acceptance, pre-launch, in-orbit, post-landing leaves). Trigger: verification stages, qualification stage, acceptance stage, pre-launch verification, in-orbit verification, commissioning, post-lan...
Scanned 9/27/2026
Install to Claude Code
npx -y skills add ashfordeOU/aero-agent-skills --skill e1002-stages --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of E1002 Stages?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/ashfordeou-e1002-stages)More formats (shields.io, HTML) on the badges page.
---
name: e1002-stages
description: "Use when defining verification stages for a product under ECSS-E-ST-10-02C: qualify, accept, verify pre-launch, in-orbit (incl. commissioning) and post-landing each with its objective and applicability to the product's launched/recovered life profile, ahead of stage-specific planning (qualification, acceptance, pre-launch, in-orbit, post-landing leaves). Trigger: verification stages, qualification stage, acceptance stage, pre-launch verification, in-orbit verification, commissioning, post-landing verification, E-ST-10-02, ecss, e-st-10c."
license: Apache-2.0
compliance: STANDARDS-REF
standards:
- id: ecss
reference-only: true
gated: false
domain: space-systems
pack: space-systems
compatibility: "agentskills.io SKILL.md; any SKILL.md host (Claude Code, Hermes, OpenClaw)"
metadata:
domain: space-systems
subdomain: ecss
tags: [ecss, e-st-10c, verification-stages, qualification, acceptance, pre-launch, in-orbit, post-landing]
version: 0.1.0
author: Aero Agent Skills
---
# ECSS Verification Stages (space-systems/ecss/e1002-stages)
Use when the task is defining which verification stages apply to a
product under ECSS-E-ST-10-02C, and what each stage is meant to
demonstrate, before the detailed stage plans (qualification, acceptance,
pre-launch, in-orbit, post-landing) are written.
## Domain quick reference
- ECSS-E-ST-10-02C clause 5.2.4.1 fixes five verification stages in a
set order, each covering a different point in the product's life.
Qualification comes first, then acceptance, then pre-launch. In-orbit
follows, and commissioning sits inside it rather than beside it.
Post-landing closes the set.
- Qualification demonstrates the design meets its requirements with
adequate margin, before any article is accepted for delivery.
Acceptance demonstrates the specific deliverable article is free of
manufacturing and workmanship defects and compliant, without consuming
the design margin qualified above.
- Pre-launch confirms the integrated flight configuration stays
compliant through transport, storage, and launch-site processing.
In-orbit confirms operational performance, including commissioning of
functions before routine operations begin. Post-landing confirms the
condition and performance of recovered or returned hardware.
- Not every stage applies to every product: qualification and acceptance
always apply; pre-launch and in-orbit apply only to a product that is
launched; post-landing applies only to a product that is recovered
after flight. A product cannot be recovered without having been
launched.
- The five stages have a fixed relative order; a stage plan or schedule
that lists them out of order (e.g. pre-launch before qualification)
signals a planning error, not a legitimate variation.
## Workflow
1. For the product under verification, capture its life profile: does it
get launched, and is it recovered or returned after flight (ground
segment equipment is typically neither).
2. Determine the applicable stages from that profile: qualification and
acceptance always apply; add pre-launch and in-orbit if launched; add
post-landing if recovered.
3. Attach each applicable stage's objective (as summarized above) to the
stage plan, so downstream stage-specific planning knows what it is
trying to demonstrate rather than just which stage it is running.
4. When a stage plan or schedule lists stages in a concrete sequence,
check that sequence against the canonical order (qualification,
acceptance, pre-launch, in-orbit, post-landing); flag any stage that
appears before a stage that should have preceded it.
5. Before closing the stage definition, confirm every applicable stage
from step 2 has a corresponding entry in the plan or schedule --
dropping post-landing for a recovered product, or in-orbit for a
launched one, leaves a gap clause 5.2.4.1 does not allow.
6. Hand the per-stage objectives to the stage-specific leaves
(e1002-qualification, e1002-acceptance, e1002-pre-launch,
e1002-in-orbit, e1002-post-landing) for detailed execution planning.
## Pitfalls
- Applying all five stages uniformly regardless of the product's life
profile, e.g. planning a post-landing stage for hardware that is never
recovered.
- Treating "recovered" as independent of "launched" -- a product cannot
reach post-landing without having gone through pre-launch and in-orbit
first.
- Accepting a stage schedule with stages out of canonical order without
flagging it as a planning error.
- Leaving an applicable stage out of the plan silently instead of
surfacing it as a missing stage.
## Behavior contract (gate 3)
The stage-objective, applicability, ordering, and completeness logic is
exercised by the gate 3 contract test: scripts/test_e1002_stages.py
against scripts/e1002_stages_logic.py (stdlib unittest, offline). Run:
python3 scripts/test_e1002_stages.py
## Compliance
- ECSS standards are freely downloadable (ESA); cite the source and
paraphrase per standards-map.yaml.