Production scheduling skill with sequencing rules, resource allocation, and schedule optimization.
Scanned 9/2/2026
Install to Claude Code
npx -y skills add a5c-ai/babysitter --skill production-scheduler --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Production Scheduler?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/a5c-ai-production-scheduler-2169add3)More formats (shields.io, HTML) on the badges page.
---
name: production-scheduler
description: Production scheduling skill with sequencing rules, resource allocation, and schedule optimization.
allowed-tools: Bash(*) Read Write Edit Glob Grep WebFetch
metadata:
author: babysitter-sdk
version: "1.0.0"
category: production-planning
backlog-id: SK-IE-029
graph:
domains: [domain:industrial-engineering]
skillAreas: [skill-area:statistical-analysis, skill-area:organizational-design, skill-area:data-analysis]
roles: [role:operations-analyst, role:research-engineer]
---
# production-scheduler
You are **production-scheduler** - a specialized skill for production scheduling including job sequencing, resource allocation, and schedule optimization.
## Overview
This skill enables AI-powered production scheduling including:
- Job shop scheduling
- Flow shop scheduling
- Priority dispatch rules (SPT, EDD, CR, SLACK)
- Makespan minimization
- Tardiness minimization
- Resource-constrained scheduling
- Gantt chart generation
- Schedule performance metrics
## Capabilities
### 1. Priority Dispatch Rules
```python
import pandas as pd
import numpy as np
from datetime import datetime, timedelta
def apply_dispatch_rules(jobs: pd.DataFrame, rule: str):
"""
Apply priority dispatch rules for job sequencing
jobs: DataFrame with columns ['job_id', 'processing_time', 'due_date', 'arrival_time']
rule: 'SPT', 'LPT', 'EDD', 'CR', 'SLACK', 'FCFS'
"""
jobs = jobs.copy()
current_time = jobs['arrival_time'].min()
if rule == 'SPT': # Shortest Processing Time
jobs['priority'] = jobs['processing_time']
sequence = jobs.sort_values('priority')
elif rule == 'LPT': # Longest Processing Time
jobs['priority'] = -jobs['processing_time']
sequence = jobs.sort_values('priority')
elif rule == 'EDD': # Earliest Due Date
jobs['priority'] = jobs['due_date']
sequence = jobs.sort_values('priority')
elif rule == 'CR': # Critical Ratio
jobs['time_remaining'] = (jobs['due_date'] - current_time).dt.total_seconds() / 3600
jobs['priority'] = jobs['time_remaining'] / jobs['processing_time']
jobs.loc[jobs['priority'] <= 0, 'priority'] = 0.001 # Urgent jobs first
sequence = jobs.sort_values('priority')
elif rule == 'SLACK': # Minimum Slack
jobs['time_remaining'] = (jobs['due_date'] - current_time).dt.total_seconds() / 3600
jobs['priority'] = jobs['time_remaining'] - jobs['processing_time']
sequence = jobs.sort_values('priority')
elif rule == 'FCFS': # First Come First Served
sequence = jobs.sort_values('arrival_time')
return {
"rule": rule,
"sequence": sequence['job_id'].tolist(),
"jobs": sequence
}
```
### 2. Schedule Performance Metrics
```python
def calculate_schedule_metrics(schedule: pd.DataFrame):
"""
Calculate comprehensive schedule performance metrics
schedule: DataFrame with ['job_id', 'start_time', 'end_time', 'due_date']
"""
schedule = schedule.copy()
# Completion time (flow time)
schedule['completion_time'] = schedule['end_time']
# Lateness (can be positive or negative)
schedule['lateness'] = (schedule['end_time'] - schedule['due_date']).dt.total_seconds() / 3600
# Tardiness (max of lateness and 0)
schedule['tardiness'] = schedule['lateness'].apply(lambda x: max(0, x))
# Earliness
schedule['earliness'] = schedule['lateness'].apply(lambda x: abs(min(0, x)))
# Binary late indicator
schedule['is_late'] = schedule['lateness'] > 0
metrics = {
'makespan': (schedule['end_time'].max() - schedule['start_time'].min()).total_seconds() / 3600,
'mean_flow_time': schedule['completion_time'].mean(),
'total_tardiness': schedule['tardiness'].sum(),
'max_tardiness': schedule['tardiness'].max(),
'number_tardy': schedule['is_late'].sum(),
'percent_on_time': (1 - schedule['is_late'].mean()) * 100,
'mean_lateness': schedule['lateness'].mean(),
'total_earliness': schedule['earliness'].sum()
}
return {
"metrics": metrics,
"schedule_detail": schedule
}
```
### 3. Job Shop Scheduling
```python
from collections import defaultdict
def job_shop_schedule(jobs: list, machines: list):
"""
Job shop scheduling using dispatching rules
jobs: list of {'job_id': str, 'operations': [(machine, processing_time), ...], 'due_date': datetime}
machines: list of machine IDs
"""
# Initialize machine availability
machine_available = {m: 0 for m in machines}
job_completion = defaultdict(lambda: 0)
schedule = []
# Process jobs operation by operation
for job in jobs:
job_id = job['job_id']
prev_end = 0
for op_idx, (machine, proc_time) in enumerate(job['operations']):
# Start time is max of machine availability and job's previous operation end
start_time = max(machine_available[machine], prev_end)
end_time = start_time + proc_time
schedule.append({
'job_id': job_id,
'operation': op_idx + 1,
'machine': machine,
'start_time': start_time,
'end_time': end_time,
'processing_time': proc_time
})
machine_available[machine] = end_time
prev_end = end_time
job_completion[job_id] = prev_end
return {
"schedule": pd.DataFrame(schedule),
"makespan": max(job_completion.values()),
"machine_utilization": calculate_machine_utilization(schedule, machines)
}
def calculate_machine_utilization(schedule: list, machines: list):
"""Calculate utilization for each machine"""
makespan = max(s['end_time'] for s in schedule)
utilization = {}
for machine in machines:
machine_ops = [s for s in schedule if s['machine'] == machine]
busy_time = sum(s['processing_time'] for s in machine_ops)
utilization[machine] = busy_time / makespan * 100 if makespan > 0 else 0
return utilization
```
### 4. Flow Shop Scheduling
```python
def johnson_algorithm(jobs: list):
"""
Johnson's algorithm for 2-machine flow shop
Minimizes makespan
jobs: list of {'job_id': str, 'machine1_time': float, 'machine2_time': float}
"""
# Separate into two sets
set_i = [] # Jobs where machine1_time <= machine2_time
set_ii = [] # Jobs where machine1_time > machine2_time
for job in jobs:
if job['machine1_time'] <= job['machine2_time']:
set_i.append(job)
else:
set_ii.append(job)
# Sort set_i by machine1_time ascending
set_i.sort(key=lambda x: x['machine1_time'])
# Sort set_ii by machine2_time descending
set_ii.sort(key=lambda x: x['machine2_time'], reverse=True)
# Optimal sequence is set_i followed by set_ii
optimal_sequence = set_i + set_ii
# Calculate makespan
m1_end = 0
m2_end = 0
schedule = []
for job in optimal_sequence:
# Machine 1 processing
m1_start = m1_end
m1_end = m1_start + job['machine1_time']
# Machine 2 processing (must wait for both machine 1 and previous job on machine 2)
m2_start = max(m1_end, m2_end)
m2_end = m2_start + job['machine2_time']
schedule.append({
'job_id': job['job_id'],
'machine1_start': m1_start,
'machine1_end': m1_end,
'machine2_start': m2_start,
'machine2_end': m2_end
})
return {
"optimal_sequence": [j['job_id'] for j in optimal_sequence],
"makespan": m2_end,
"schedule": schedule
}
```
### 5. Resource-Constrained Scheduling
```python
def resource_constrained_schedule(tasks: list, resources: dict, dependencies: dict):
"""
Schedule tasks with resource constraints and dependencies
tasks: list of {'task_id': str, 'duration': float, 'resources': {resource: amount}}
resources: {resource: available_amount}
dependencies: {task_id: [predecessor_task_ids]}
"""
# Track task status
scheduled = {}
resource_timeline = {r: [] for r in resources}
# Get tasks in topological order
remaining = set(t['task_id'] for t in tasks)
task_dict = {t['task_id']: t for t in tasks}
current_time = 0
max_time = 1000 # Safety limit
while remaining and current_time < max_time:
# Find eligible tasks (all predecessors complete)
eligible = []
for task_id in remaining:
predecessors = dependencies.get(task_id, [])
if all(p in scheduled for p in predecessors):
# Check earliest start (after predecessors)
earliest = 0
for p in predecessors:
earliest = max(earliest, scheduled[p]['end_time'])
eligible.append((task_id, earliest))
# Try to schedule eligible tasks
for task_id, earliest in sorted(eligible, key=lambda x: x[1]):
task = task_dict[task_id]
start_time = max(earliest, current_time)
# Check resource availability
can_schedule = True
for resource, amount in task.get('resources', {}).items():
if amount > resources.get(resource, 0):
can_schedule = False
break
if can_schedule:
end_time = start_time + task['duration']
scheduled[task_id] = {
'task_id': task_id,
'start_time': start_time,
'end_time': end_time,
'duration': task['duration']
}
remaining.remove(task_id)
current_time += 1
return {
"schedule": list(scheduled.values()),
"makespan": max(s['end_time'] for s in scheduled.values()) if scheduled else 0,
"unscheduled": list(remaining)
}
```
### 6. Gantt Chart Generation
```python
def generate_gantt_data(schedule: pd.DataFrame, group_by: str = 'machine'):
"""
Generate data for Gantt chart visualization
schedule: DataFrame with columns appropriate for group_by
group_by: 'machine' or 'job'
"""
gantt_data = []
for _, row in schedule.iterrows():
gantt_data.append({
'Task': row[group_by] if group_by in row else row.get('job_id', 'Unknown'),
'Start': row['start_time'],
'Finish': row['end_time'],
'Resource': row.get('job_id', row.get('machine', 'Unknown')),
'Duration': row['end_time'] - row['start_time']
})
return {
"gantt_data": gantt_data,
"timeline_start": min(g['Start'] for g in gantt_data),
"timeline_end": max(g['Finish'] for g in gantt_data),
"resources": list(set(g['Resource'] for g in gantt_data))
}
```
## Process Integration
This skill integrates with the following processes:
- `production-scheduling-optimization.js`
- `capacity-planning-analysis.js`
## Output Format
```json
{
"schedule": {
"sequence": ["J1", "J3", "J2", "J4"],
"rule_applied": "EDD"
},
"metrics": {
"makespan": 42,
"mean_flow_time": 24.5,
"total_tardiness": 8,
"percent_on_time": 75
},
"gantt_data": [...],
"recommendations": [
"Consider SPT rule to minimize flow time",
"Job J4 is critical path - prioritize"
]
}
```
## Best Practices
1. **Match rule to objective** - SPT for flow time, EDD for due dates
2. **Consider setup times** - Sequence-dependent setups matter
3. **Build in buffers** - Account for variability
4. **Monitor actual vs. planned** - Adjust rules based on performance
5. **Communicate changes** - Schedule visibility is critical
6. **Review regularly** - Reschedule as conditions change
## Constraints
- Static scheduling assumes known job arrivals
- Setup times may be sequence-dependent
- Resource constraints add complexity
- Real-time adjustments needed for disruptions