Use when you must decide the offline schedulability of a periodic hard-real-time task set: compute the processor utilization of (C, T) tasks with implicit deadlines, apply the Liu-Layland utilization bound for rate-monotonic fixed-priority scheduling, run the exact iterative response-time analysis task by task, and test earliest-deadline-first feasibility with the full-utilization condition. Produces the utilization, the RM bound verdict, the exact response times with an RM feasibility verdic...
Scanned 9/27/2026
Install to Claude Code
npx -y skills add ashfordeOU/aero-agent-skills --skill real-time-scheduling --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Real Time Scheduling?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/ashfordeou-real-time-scheduling)More formats (shields.io, HTML) on the badges page.
---
name: real-time-scheduling
description: "Use when you must decide the offline schedulability of a periodic hard-real-time task set: compute the processor utilization of (C, T) tasks with implicit deadlines, apply the Liu-Layland utilization bound for rate-monotonic fixed-priority scheduling, run the exact iterative response-time analysis task by task, and test earliest-deadline-first feasibility with the full-utilization condition. Produces the utilization, the RM bound verdict, the exact response times with an RM feasibility verdict, the EDF feasibility verdict, and an overall scheduling verdict for avionics process and partition task sets. Trigger: rate monotonic scheduling, response time analysis, liu layland bound, earliest deadline first, cpu utilization, fixed priority scheduling, schedulability, worst case execution time."
license: Apache-2.0
compliance: STANDARDS-REF
standards:
- id: do-178c
reference-only: true
gated: false
domain: avionics
pack: fsw
compatibility: "agentskills.io SKILL.md; any SKILL.md host (Claude Code, Hermes, OpenClaw)"
metadata:
domain: avionics
subdomain: fsw
tags: [real-time-scheduling, rate-monotonic-scheduling, response-time-analysis, liu-layland-bound, earliest-deadline-first, cpu-utilization, fixed-priority-scheduling]
version: 0.1.0
author: AeroSkills
---
# Real-Time Scheduling (avionics/fsw/real-time-scheduling)
Use when you must decide whether a periodic hard-real-time task set can
meet every deadline on a single processor, before it ever runs. Each
task is a (C, T) pair: worst-case execution time C and period T, with
the implicit deadline D = T, all in one time unit. This leaf implements
the standard public feasibility mathematics (Liu and Layland 1973 plus
exact iterative response-time analysis) in pure Python stdlib: the
processor utilization, the Liu-Layland sufficient bound for
rate-monotonic fixed-priority scheduling, exact per-task response times
with an RM verdict, and the earliest-deadline-first full-utilization
verdict. It schedules the processes and partitions inside an ARINC 653
style avionics software partition layout, pairing with
avionics/ima/ima-partitioning, which owns the major-frame cyclic window
arithmetic that surrounds this leaf's process set.
## Domain quick reference
- Task set convention: n tasks, each (C_i, T_i) with implicit deadline
D_i = T_i, all in the same time unit. Shorter period means higher
priority under RM; equal periods are broken by list index (the
earlier task in the list is higher priority).
- Utilization: U = sum_i C_i / T_i. This is the fraction of the
processor the task set demands in the long run.
- Liu-Layland bound: U_rm(n) = n (2^(1/n) - 1). Anchor values:
U_rm(2) = 0.828427, U_rm(3) = 0.779763, U_rm(4) = 0.756828, and
U_rm(1) = 1. The bound decreases toward ln 2 ~ 0.693 as n grows.
- RM sufficient test: if U <= U_rm(n) the set is feasible under RM. The
bound is sufficient, not necessary: a set with U above the bound may
still be RM-feasible, which is exactly when the exact analysis earns
its keep.
- Exact RM response time of task i (fixed-point iteration):
R_i = C_i + sum_{j in hp(i)} ceil(R_i / T_j) * C_j, iterated from
R_i = C_i until the value stops changing, where hp(i) is the set of
higher-priority tasks. RM is feasible iff every converged R_i <= T_i.
- Divergence handling: the response-time sequence is monotone
non-decreasing, so when an iterate grows past the task period, or
past the cap 1000 * max(T) of the set, it can never converge to a
schedulable value and the analysis reports divergence. A diverging or
deadline-crossing task makes the whole set RM-infeasible.
- EDF feasibility (implicit deadlines): U <= 1 is necessary and
sufficient, because EDF is optimal among all scheduling algorithms on
a single processor.
- Scheduling verdicts: "RM-guaranteed-by-UB" when the bound test
passes; "RM-exact-feasible (UB inconclusive)" when the bound test
fails but exact response-time analysis converges within every period;
"EDF-feasible-only" when RM exact analysis fails but EDF can schedule
the U <= 1 set; "RM-infeasible" otherwise.
- Scope notes: WCET estimation, jitter and blocking analysis, and
arbitrary-deadline response-time extensions are out of scope; the
model is the classic implicit-deadline periodic task set. ARINC 653
partition schedule windows and message bus response windows are not
this leaf.
## Workflow
1. Collect the task set as a list of (C, T) pairs in one time unit,
worst-case execution time and period each, implicit deadline
D = T. Every C and T must be positive; an empty list, a
non-positive value, or a malformed entry raises ValueError from
every function.
2. Compute the processor demand: utilization(tasks) returns U. If
U > 1 the processor is oversubscribed: no single-processor
scheduling algorithm can work, and EDF feasibility will fail.
3. Run the cheap sufficient test first: rm_ub_feasible(tasks) applies
the Liu-Layland bound U <= U_rm(n). A True verdict closes the case
(RM is guaranteed). A False verdict is inconclusive, not a failure.
4. When the bound is inconclusive, run the exact analysis:
rm_response_times(tasks) returns the converged R_i list, or None
when the iteration diverges (an iterate exceeded its period or the
1000 * max(T) cap), and rm_feasible(tasks) gives the exact RM
verdict. This is where rate-monotonic analysis beats the
utilization bound: a set that fails step 3 can still pass here.
5. Check the EDF alternative: edf_feasible(tasks) reports whether U
<= 1, which for implicit-deadline sets is a complete EDF test.
6. Run scheduling_summary(tasks) once to gather every result: keys
utilization, n_tasks, liu_layland_bound, rm_ub_verdict,
rm_exact_response_times, rm_exact_feasible, edf_feasible, and a
single verdict string.
7. Record the verdict and the response times in the scheduling
analysis artifact for the certification package; re-run the
contract test after any change to the task set.
## Worked example
Spec task set A, [(1, 3), (1, 4), (2, 8)] (times in ms):
- Utilization: U = 1/3 + 1/4 + 2/8 = 0.8333333333333333.
- Liu-Layland bound for 3 tasks: 0.7797631496846196, so U > bound and
rm_ub_feasible returns False: the bound test is inconclusive.
- Exact response-time analysis converges:
rm_response_times(A) = [1.0, 2.0, 6.0] ms, all within their periods
(3, 4, 8 ms), so rm_feasible returns True.
- EDF: U = 0.8333 <= 1, so edf_feasible returns True.
- scheduling_summary(A)["verdict"] is
"RM-exact-feasible (UB inconclusive)": the key demonstration that
response-time analysis proves schedulability where the Liu-Layland
bound stays silent.
Set B, [(2, 3), (2, 5), (2, 7)]: U = 1.3523809523809525 > 1, so
edf_feasible is False, rm_response_times returns None (the second task
response time crosses its period and the iteration diverges), and the
verdict is "RM-infeasible".
Set C, [(1, 5), (1, 6), (2, 10)]: U = 0.5666666666666667 <= 0.7798, so
rm_ub_feasible is True and the verdict is "RM-guaranteed-by-UB"; the
exact analysis confirms with response times [1.0, 2.0, 4.0].
## Verification
- Confirm the Liu-Layland anchors: liu_layland_bound(2) = 0.828427,
liu_layland_bound(3) = 0.779763, liu_layland_bound(4) = 0.756828
(each within 1e-5).
- Confirm worked set A gives U 0.8333, rm_ub_feasible False (bound
inconclusive), rm_response_times [1.0, 2.0, 6.0] with rm_feasible
True, edf_feasible True, verdict "RM-exact-feasible (UB
inconclusive)".
- Confirm worked set B gives U 1.3524 > 1, edf_feasible False, RTA
divergence (None), rm_feasible False.
- Confirm worked set C gives U 0.5667, rm_ub_feasible True, response
times [1.0, 2.0, 4.0], verdict "RM-guaranteed-by-UB".
- Confirm adding a task raises U and doubling a task's C doubles that
task's utilization contribution.
- Confirm an empty task list, C <= 0, T <= 0, malformed or
non-numeric entries, and a fractional task count raise ValueError
from every public function.
- Confirm identical outputs run to run (no randomness anywhere).
- Run the deterministic contract test offline: python3
scripts/test_real_time_scheduling.py (35 tests).
## Related leaves
- avionics/ima/ima-partitioning: ARINC 653 major-frame cyclic window
arithmetic; this leaf schedules the periodic process sets that run
inside those partition windows.
- avionics/fsw/cfs-architecture: flight software application
routing; its periodic applications carry the C and T budgets this
leaf checks.
- avionics/data-bus/mil-std-1553: bus command/response protocol
timing; its response-window concept is a bus term, not a task
response time.
## Pitfalls
- Reading a failed utilization bound as infeasibility: the Liu-Layland
bound is sufficient, not necessary - worked set A fails the bound
(U 0.8333 above U_rm(3) 0.7798) yet is exactly RM-feasible with
response times [1.0, 2.0, 6.0], so a False rm_ub_feasible verdict
means run the exact analysis, not declare the set unschedulable.
- Treating divergence as a numeric hiccup: the response-time sequence
is monotone non-decreasing, so an iterate that crosses its period
or the 1000 * max(T) cap can never converge - rm_response_times
returns None and the whole set is RM-infeasible (set B), which is a
verdict, not an error to paper over.
- Mixing time units in one task set: every C_i and T_i must share one
time unit and the implicit deadline is D_i = T_i - a task listed in
seconds against milliseconds, or with an explicit different
deadline, is outside this leaf's model and corrupts U and the
response-time iteration.
- Ignoring the priority order: RM assigns priority by shorter period,
with equal periods broken by list index, and the exact analysis
sums only over higher-priority tasks hp(i) - the response-time
result is only valid for the task list in RM priority order.
- Assuming EDF always saves the set: EDF is complete only for U <= 1,
so an over-subscribed set (U 1.3524, set B) is infeasible under any
single-processor algorithm, and the "EDF-feasible-only" verdict
means the exact RM analysis failed - the schedule then needs an EDF
runtime, not rate-monotonic priorities.
- Routing adjacent timing domains here: WCET estimation, jitter and
blocking analysis, arbitrary-deadline extensions, ARINC 653
partition schedule windows (ima/ima-partitioning), and bus response
windows (data-bus/mil-std-1553) are not this leaf's classic
implicit-deadline periodic model.
## Behavior contract (gate 3)
Run the deterministic contract test (stdlib unittest, offline, no
network, exits 0):
python3 scripts/test_real_time_scheduling.py
The test covers the Liu-Layland anchors U_rm(2/3/4), the three worked
task sets A, B and C from the spec plus an EDF-feasible-only set D,
exact response times with integrality for integer input, divergence
detection returning None, single-task closed forms (R = C, feasible iff
C <= T), utilization monotonicity and doubling, the EDF unit-utilization
boundary, the exact convenience-dict keys, ValueError rejection of
empty, non-positive and malformed task lists, and run-to-run
determinism.
## Compliance
- Standards referenced, not reproduced: DO-178C (avionics software
lifecycle, including scheduling analysis of the software partition
task sets) is listed reference-only per standards-map.yaml; the
feasibility mathematics above is pure public science (Liu and
Layland, 1973), summary-only.
- ARINC 653 is not in standards-map.yaml and is not needed: the
process-level scheduling theory is independent of the partition
standard text.