Draft and audit the software product assurance programme and its plan (SPAP) under ECSS-Q-ST-80C Rev.2: grade a plan against the Annex B outline with conditional sections switched on by scope, check the assurance organisation for a named lead, an independent reporting line and backed supplier delegation, check supplier flow-down and monitoring against the software category, grade methods and tools by their effect on the executable, and state the plan maturity owed at each review. Use when a s...
Scanned 9/27/2026
Install to Claude Code
npx -y skills add ashfordeOU/aero-agent-skills --skill q80-software-product-assurance-plan --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Q80 Software Product Assurance Plan?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/ashfordeou-q80-software-product-assurance-plan)More formats (shields.io, HTML) on the badges page.
---
name: q80-software-product-assurance-plan
description: "Draft and audit the software product assurance programme and its plan (SPAP) under ECSS-Q-ST-80C Rev.2: grade a plan against the Annex B outline with conditional sections switched on by scope, check the assurance organisation for a named lead, an independent reporting line and backed supplier delegation, check supplier flow-down and monitoring against the software category, grade methods and tools by their effect on the executable, and state the plan maturity owed at each review. Use when a supplier writes or updates its SPAP or a customer reviews one. Trigger: spap, software-product-assurance-plan, q80-spap-drd, spa-organisation-independence, software-supplier-flow-down, spa-tool-justification."
license: Apache-2.0
compliance: STANDARDS-REF
standards:
- id: ecss
reference-only: true
gated: false
domain: space-systems
pack: space-systems
compatibility: "agentskills.io SKILL.md; any SKILL.md host (Claude Code, Hermes, OpenClaw)"
clauses:
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.2.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.2.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.2.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.3.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.3.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.4.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.4.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.5.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.5.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.5.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.1.5.4
items: [a, b]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.1.1
items: [a, b]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.1.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.1.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.1.4
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.1.5
items: [a, b]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.4
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.7.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.2.7.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.3.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.1.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.1.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.1.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.2.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.2.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.6.2.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.2.1
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.2.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.2.3
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.2.4
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.3.1
items: [a, b]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.3.2
items: [a]
relation: verifies
- standard: ECSS-Q-ST-80C Rev.2
clause: 5.7.3.3
items: [a]
relation: verifies
metadata:
domain: space-systems
subdomain: ecss
tags: [ecss, q-st-80c, q80-software-product-assurance-plan, spap, software-product-assurance-plan, q80-spap-drd, spa-organisation-independence, software-supplier-flow-down, spa-tool-justification]
version: 0.1.0
author: Aero Agent Skills
---
# ECSS Software Product Assurance Plan (space-systems/ecss/q80-software-product-assurance-plan)
Use when the task is the software product assurance (SPA) programme of
ECSS-Q-ST-80C Rev.2 (30 April 2025) and the plan that documents it, the
Software Product Assurance Plan (SPAP) defined by the document requirements
definition (DRD) in Annex B. The programme itself is clause 5: organisation
and responsibility, programme management, risk and critical items, supplier
selection and control, procurement, tools and supporting environment, and
process assessment and improvement.
## Domain quick reference
- The plan is where every other obligation is first promised. Its last
section is a compliance matrix to the standard, so an incomplete plan
makes an incomplete matrix before any work is done.
- The outline has fixed sections and conditional ones. Supplier control,
operations and maintenance, security and reuse sections are owed only
when the project has that scope; grading a plan without scope turned on
either invents findings or misses real ones.
- A present section is not an answered section. A heading followed by two
lines does not describe an organisation, a quality model or a metrics
programme.
- Independence is about the reporting line. The assurance lead reports to
the project manager, through the product assurance manager where there
is one, never through the software development line, and never holds
the development lead role at the same time.
- Delegating assurance tasks to a supplier is allowed only when the
supplier's own plan is held and reviewed.
- Supplier control is proportionate: category, assurance requirements and
the supplier's plan flow down in every case; the depth of monitoring
rises with the category.
- A tool matters by what it can do to the product. A generator or compiler
can put a defect into the executable; a verification tool can hide one.
Those need qualification evidence for categories A and B; a documentation
tool needs only its justification.
- The plan is issued for the system requirements review (SRR), updated for
the preliminary and critical design reviews (PDR, CDR) and maintained
through qualification (QR), acceptance (AR) and operational readiness
(ORR).
## Workflow
1. Fix the scope: suppliers, operations and maintenance, security
sensitivity, reuse. Each switches a conditional section on.
2. Grade the draft with `assess_spap` against the Annex B outline:
missing sections, thin sections, sections not owed, and ids that are
not in the outline at all. The plan answers the project's assurance
requirements, and may stand alone or be a section of the supplier's
overall product assurance plan. Every internal manual, standard or
procedure it refers to counts as part of the programme and has to be
available to the reviewer.
3. Check the organisation with `check_organisation`: an organisation for
software development in which each person has defined tasks; the
responsibility, authority and working relations of everyone who
manages, does or checks work that affects software quality, written
down; the responsibilities and interfaces of every internal and
external organisation on the project, written down; and enough
resources for the assurance tasks.
4. Check the assurance lead: a named person; answering to the project
manager, via the product assurance manager where there is one,
never through the development line; with the authority and
independence to set up and sustain the assurance programme; with direct
access to higher management when needed. Audits and reviews, of
both products and processes, are done by people who did not do the work.
5. Check any delegation of assurance work to a lower-tier supplier: it
is documented and controlled, backed by that supplier's own plan held
and reviewed, and the plan states that responsibility to the customer
stays with this supplier.
6. Check each supplier with `check_supplier_control`: category and
requirements flowed down, plan received, pre-award assessment,
monitoring depth for the category.
7. Check staffing and training: the project requirements were reviewed
early enough to acquire or build the skills needed, in a training plan;
training subjects follow from the tools, techniques, methods and
computers actually used; the people on each planned task have the right
mix of skills and training by the time the task starts; that training
covers security analysis and audit, security engineering, security
assurance methods and tools, and the project's own security rules and
procedures; and training records are kept.
8. Check the quality model: the software quality requirements are
specified through one, built on functionality, reliability,
maintainability, reusability, suitability for safety, security,
usability, efficiency, portability and development effectiveness.
9. Check the plan links software risks into the project risk policy of
ECSS-M-ST-80 rather than running a separate register, holds an audit
plan and schedule run as the general quality assurance standard
ECSS-Q-ST-10 sets out for audits, and handles software alerts through
that same standard's alert process.
10. Grade the methods and tools with `assess_tools` against the category.
The methods and tools for every development activity, from
requirements analysis and modelling through coding and testing to
configuration management, verification and assurance, are proposed by
the supplier and accepted by the customer. Each choice is justified by a
test or a written assessment showing the team is experienced or
trained in it, that it suits the product's function and operation,
that it will stay available through development and maintenance, and
that it suits the product's security sensitivity. Their correct use is
checked and reported.
11. Check the development environment: chosen against availability,
compatibility, performance, maintenance, durability and consistency
with the operational equipment, the category and the security
sensitivity, the security regulations that apply, support
documentation, acceptance and warranty, installation and training,
maintenance and evolution, copyright, and dependence on one vendor;
its fitness justified in writing; and its availability to the
developers confirmed before each phase starts.
12. Check process assessment and improvement: how capable the
processes in use are, including those that units outside the team
provide, is monitored and controlled; each assessment has a documented
model and method conforming to ISO/IEC 33002:2015, a model, method,
scope, results and assessors that the customer set or recognised and
that were checked against the project requirements, and a competent
assessor. Results feed back into the processes, into where the
project is heading and into technology needs; earlier results are used;
improvement follows a documented improvement process; and the
improvement is shown with evidence.
13. Check the compliance matrix delivered with the plan: one row per
applicable assurance requirement, and for each a reference to the
document holding its expected output.
14. State the maturity the plan owes at the next review with
`plan_maturity_due` and list what must change to reach it. The plan
is revised at every milestone so the next phase's work is fully
defined, and before the acceptance review it is extended with the
quality measures for operations and maintenance, or a separate plan
for them is issued.
## Obligations
| Item | Step |
|---|---|
| ECSS-Q-ST-80C Rev.2 5.1.1a | 3 |
| ECSS-Q-ST-80C Rev.2 5.1.2.1a | 3 |
| ECSS-Q-ST-80C Rev.2 5.1.2.2a | 3 |
| ECSS-Q-ST-80C Rev.2 5.1.2.3a | 5 |
| ECSS-Q-ST-80C Rev.2 5.1.3.1a | 3 |
| ECSS-Q-ST-80C Rev.2 5.1.3.2a | 4 |
| ECSS-Q-ST-80C Rev.2 5.1.4.1a | 4 |
| ECSS-Q-ST-80C Rev.2 5.1.4.2a | 4 |
| ECSS-Q-ST-80C Rev.2 5.1.5.1a | 7 |
| ECSS-Q-ST-80C Rev.2 5.1.5.2a | 7 |
| ECSS-Q-ST-80C Rev.2 5.1.5.3a | 7 |
| ECSS-Q-ST-80C Rev.2 5.1.5.4a | 7 |
| ECSS-Q-ST-80C Rev.2 5.1.5.4b | 7 |
| ECSS-Q-ST-80C Rev.2 5.2.1.1a | 2 |
| ECSS-Q-ST-80C Rev.2 5.2.1.1b | 2 |
| ECSS-Q-ST-80C Rev.2 5.2.1.2a | 2 |
| ECSS-Q-ST-80C Rev.2 5.2.1.3a | 14 |
| ECSS-Q-ST-80C Rev.2 5.2.1.4a | 14 |
| ECSS-Q-ST-80C Rev.2 5.2.1.5a | 13 |
| ECSS-Q-ST-80C Rev.2 5.2.1.5b | 13 |
| ECSS-Q-ST-80C Rev.2 5.2.3a | 9 |
| ECSS-Q-ST-80C Rev.2 5.2.4a | 9 |
| ECSS-Q-ST-80C Rev.2 5.2.7.1a | 8 |
| ECSS-Q-ST-80C Rev.2 5.2.7.2a | 8 |
| ECSS-Q-ST-80C Rev.2 5.3.1a | 9 |
| ECSS-Q-ST-80C Rev.2 5.6.1.1a | 10 |
| ECSS-Q-ST-80C Rev.2 5.6.1.2a | 10 |
| ECSS-Q-ST-80C Rev.2 5.6.1.3a | 10 |
| ECSS-Q-ST-80C Rev.2 5.6.2.1a | 11 |
| ECSS-Q-ST-80C Rev.2 5.6.2.2a | 11 |
| ECSS-Q-ST-80C Rev.2 5.6.2.3a | 11 |
| ECSS-Q-ST-80C Rev.2 5.7.1a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.2.1a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.2.2a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.2.3a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.2.4a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.3.1a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.3.1b | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.3.2a | 12 |
| ECSS-Q-ST-80C Rev.2 5.7.3.3a | 12 |
## Pitfalls
- Grading against the full outline regardless of scope.
- Accepting an organisation chart as independence. The line of report is
what is checked, not the box the lead sits in.
- Letting a supplier's category be lower than the product it feeds
without a recorded justification.
- Justifying a code generator by popularity. Its effect on the executable
decides what evidence it needs.
- Leaving the compliance matrix section for last. It is the section the
customer reads first.
## Stop gate: human sign-off required
The agent drafts; it does not decide. Stop and hand the draft to a named
human before any of these leave the working folder:
- The SPAP, or any update of it, submitted to the customer.
- The statement of the assurance organisation and the independence of the
assurance lead.
- Any delegation of assurance tasks to a supplier, and any tool
qualification argument.
Mark every such output as a draft, list the open questions for the
reviewer, and end with the line: STOP: human sign-off required before
submission.
## Behavior contract (gate 3)
The section id normalisation, the outline with its conditional sections,
the plan grading with missing, thin and not-owed sections and a coverage
fraction, the organisation and independence findings, the supplier
flow-down and monitoring check, the tool grading by impact and category and
the plan maturity per review are exercised by the gate 3 contract test:
scripts/test_q80_software_product_assurance_plan.py against
scripts/q80_software_product_assurance_plan_logic.py (stdlib unittest,
offline). Run: python3 scripts/test_q80_software_product_assurance_plan.py
## Compliance
- ECSS standards are freely downloadable (ESA); cite ECSS-Q-ST-80C Rev.2
(30 April 2025) as the source and paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.