Use when plan the spacecraft-charging protection programme required by ECSS-E-ST-20-06C clause 5: score an early charging-hazard assessment for each item from its orbital-environment severity, its surface-exposure kind and its exposed area, categorize the electrostatic-discharge risk into a band, derive the mitigation measures and the verification-method set that band demands, compare the planned project-review milestone against the latest acceptable one, and report every item with no plan en...
Scanned 9/27/2026
Install to Claude Code
npx -y skills add ashfordeOU/aero-agent-skills --skill e2006-charging-protection-programme --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of E2006 Charging Protection Programme?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/ashfordeou-e2006-charging-protection-programme)More formats (shields.io, HTML) on the badges page.
---
name: e2006-charging-protection-programme
description: "Use when plan the spacecraft-charging protection programme required by ECSS-E-ST-20-06C clause 5: score an early charging-hazard assessment for each item from its orbital-environment severity, its surface-exposure kind and its exposed area, categorize the electrostatic-discharge risk into a band, derive the mitigation measures and the verification-method set that band demands, compare the planned project-review milestone against the latest acceptable one, and report every item with no plan entry, an uncovered measure or a late milestone. Trigger: ecss, e-st-20-06c, charging-hazard-assessment, charging-mitigation-plan, verification-method-assignment, electrostatic-discharge-risk, protection-programme-milestones, spacecraft-charging-protection."
license: Apache-2.0
compliance: STANDARDS-REF
standards:
- id: ecss
reference-only: true
gated: false
domain: space-systems
pack: space-systems
compatibility: "agentskills.io SKILL.md; any SKILL.md host (Claude Code, Hermes, OpenClaw)"
metadata:
domain: space-systems
subdomain: ecss
tags: [ecss, e-st-20-electrical-scope, e2006-charging-protection-programme, e-st-20-06c, charging-hazard-assessment, charging-mitigation-plan, verification-method-assignment, electrostatic-discharge-risk, protection-programme-milestones]
version: 0.1.0
author: Aero Agent Skills
---
# ECSS Spacecraft Charging — Protection Programme (space-systems/ecss/e2006-charging-protection-programme)
Use when the task is clause 5 of ECSS-E-ST-20-06C: standing up the
charging protection programme — an early hazard assessment per item, a
mitigation plan that follows from it, and closure of that plan through
measurement, inspection, testing and analysis booked against the right
project review.
## Domain quick reference
- The hazard of an item is not a property of the orbit alone. Three
inputs combine: how energetic the charging drivers of the orbital
environment are, how exposed the item is to the accumulating surface
charge, and how much area is exposed. A geostationary orbit is the
severe end of the first axis, an equatorial low orbit the benign end;
an exposed dielectric is the severe end of the second, a shielded
internal harness the benign end. The area contribution saturates:
past roughly one square metre a larger surface adds little, while a
very small patch pulls the index down markedly.
- The index is banded — negligible, low, significant, severe — and the
band, not the raw number, drives the programme. A band edge is
inclusive: an index that lands exactly on it belongs to the higher
band, and an index a few units in the last place below the edge is
still the higher band, because that difference is representation
error and not engineering margin.
- Each band demands a set of mitigation measures and a set of
verification methods. The severe band demands conductive surface
treatment, grounding and bonding, and shielding or filtering, closed
by all four verification methods including physical measurement. The
negligible band demands no mitigation measure and closes by analysis
alone. Extra measures beyond the demanded set are allowed; missing
ones are findings.
- Timing is part of the requirement, not a project convenience. The
hazard assessment is an early activity — for a severe item it is due
at the first system review, so that the mitigation it drives can
still change the design; the mitigation plan follows one review
later, and verification closure lands by qualification or acceptance
depending on the band. A milestone planned later than the latest
acceptable one is a finding even when the activity is otherwise
complete.
## Workflow
1. Inventory every item with an external or partially exposed surface.
Capture its orbital environment, its exposure kind and its exposed
area. Reject an unrecognized environment or exposure kind rather
than defaulting it.
2. Score the hazard index for each item and categorize it into a risk
band. Report the index alongside the band so a borderline item is
visible.
3. Look the item up in the protection plan. An item with a non-
negligible risk and no plan entry is a finding on its own — absence
of an entry is not evidence of absence of hazard.
4. Compare the declared mitigation measures against the set the band
demands and report the gap by name.
5. Compare the declared verification methods against the set the band
demands. A severe item that closes on analysis alone, with no
physical measurement, is the characteristic gap.
6. For each programme activity — hazard assessment, mitigation plan,
verification closure — compare the planned project review against
the latest acceptable one for that band. An unplanned activity and
a late activity are both findings.
7. The programme is compliant only when every list is empty.
## Pitfalls
- Scoring the hazard from the orbit alone. Two items in the same orbit
differ by an order of magnitude in exposure, and a blanket orbital
categorization drags shielded internal hardware into the severe band
while it hides a small exposed dielectric.
- Widening a band edge to make a borderline item pass. The edge is the
engineering limit; the only thing the comparison absorbs is the
floating-point error of the arithmetic that produced the index.
- Closing a severe item on analysis alone. The band demands physical
evidence — measurement and inspection as well as testing — and a
plan that lists only the desk method has not closed it.
- Booking the hazard assessment late. Its whole value is that it lands
before the design is frozen; an assessment presented at the critical
review can no longer drive the mitigation it recommends.
- Reading an item that is absent from the plan as unaffected. An
unlisted item is an unassessed item and appears in the findings with
its scored risk attached.
## Behavior contract (gate 3)
The hazard index, risk bands and their edges, mitigation and
verification coverage, milestone schedule check and aggregate
programme report are exercised by the gate 3 contract test:
scripts/test_e2006_charging_protection_programme.py against
scripts/e2006_charging_protection_programme_logic.py (stdlib unittest,
offline). Run:
python3 scripts/test_e2006_charging_protection_programme.py
## Compliance
- ECSS standards are freely downloadable (ESA); cite the source and
paraphrase per standards-map.yaml.
- compliance: STANDARDS-REF, gated: false.