Use when performing database schema changes, data migrations, large table modifications, or when zero-downtime deployment is required - guides systematic, reversible database changes with rollback planning
Scanned 2/12/2026
Install via CLI
openskills install JeremyDev87/codingbuddy---
name: database-migration
description: Use when performing database schema changes, data migrations, large table modifications, or when zero-downtime deployment is required - guides systematic, reversible database changes with rollback planning
---
# Database Migration
## Overview
Database migrations are high-risk operations that can cause data loss, service outages, and inconsistencies. Rushed migrations fail; systematic migrations succeed.
**Core principle:** ALWAYS have a tested rollback plan before executing any migration. No migration is too small for planning.
**Violating the letter of this process is violating the spirit of database migration safety.**
## First 5 Minutes Checklist (Emergency Migration)
**Use this when urgent schema change needed. Don't think, follow the list.**
| Minute | Action | Output |
|--------|--------|--------|
| 0-1 | Identify what needs to change and why | `change_classified` |
| 1-2 | Check if change is reversible | `rollback_possible` or `requires_planning` |
| 2-3 | Estimate rows affected and lock impact | `impact_assessed` |
| 3-4 | Create backup of affected tables | `backup_verified` |
| 4-5 | If >1M rows or DDL lock: STOP, use full process | `proceed` or `escalate` |
**After 5 minutes:** Proceed to Phase 2 (Plan) if safe, otherwise follow full process.
## The Iron Law
```
NO MIGRATION WITHOUT A TESTED ROLLBACK PLAN FIRST
```
If you haven't verified you can undo the change, you cannot execute the migration.
## When to Use
Use for ANY database change:
- Schema modifications (ADD/DROP/ALTER)
- Large data transformations
- Index creation or removal
- Foreign key changes
- Data type conversions
- Table splitting or merging
**Use this ESPECIALLY when:**
- Zero-downtime is required (production systems)
- Table has >1 million rows
- Change affects foreign key relationships
- Multiple tables need coordinated changes
- Rollback must preserve data
**Don't skip when:**
- "It's just adding a column" (NULL vs NOT NULL matters)
- "We're in a hurry" (rushed migrations cause outages)
- "It's a small table" (today's small table is tomorrow's large table)
## When NOT to Use
This skill is for **systematic database migrations**. Don't use it for:
- **Local development only** - Experiment freely in dev
- **Seed data insertion** - Use standard insert scripts
- **Query optimization** - Use systematic-debugging for investigation
- **New greenfield tables** - Simple CREATE TABLE is fine
**Key distinction:** This skill manages schema and data changes in systems with existing data. For new projects without data, standard migration tools suffice.
## The Six Phases
You MUST complete each phase before proceeding to the next.
```dot
digraph database_migration {
rankdir=TB;
node [shape=box];
"1. Assess" -> "2. Plan";
"2. Plan" -> "3. Prepare";
"3. Prepare" -> "4. Execute";
"4. Execute" -> "5. Verify";
"5. Verify" -> "6. Document";
"Skip Phase?" [shape=diamond];
"2. Plan" -> "Skip Phase?" [style=dashed, label="tempted?"];
"Skip Phase?" -> "STOP" [label="NO"];
"STOP" [shape=doublecircle, color=red];
}
```
### Phase 1: Assess
**Classify the migration:**
1. **Identify Migration Type**
- Schema-only (DDL): ADD COLUMN, CREATE INDEX, etc.
- Data-only (DML): UPDATE, INSERT, DELETE
- Combined: Schema + data transformation
- Destructive: DROP, TRUNCATE, type narrowing
2. **Measure Impact**
- Count rows affected: `SELECT COUNT(*) FROM table`
- Estimate lock duration
- Check table size and index count
- Identify peak traffic windows
3. **Classify Risk Level**
| Risk | Criteria | Approach |
|------|----------|----------|
| **Low** | <100K rows, additive only, nullable | Direct migration |
| **Medium** | 100K-10M rows, non-destructive | Batched migration |
| **High** | >10M rows, schema + data | Expand-Contract |
| **Critical** | Destructive, FK changes | Blue-Green or Shadow |
**Completion criteria:**
- [ ] `migration_type_identified` - DDL/DML/Combined/Destructive
- [ ] `risk_level_classified` - Low/Medium/High/Critical
- [ ] `impact_measured` - Row count, lock estimate
### Phase 2: Plan
**Design the migration strategy:**
See `expand-contract-patterns.md` for zero-downtime techniques.
1. **Choose Migration Pattern**
| Pattern | Use When | Downtime |
|---------|----------|----------|
| **Direct** | Low risk, off-peak | Brief |
| **Batched** | Medium risk, large tables | None |
| **Expand-Contract** | High risk, zero-downtime required | None |
| **Blue-Green** | Critical, full schema redesign | Switchover only |
| **Shadow Table** | Type changes, column renames | Cutover only |
1. **Design Rollback Strategy**
See `rollback-strategies.md` for detailed procedures.
| Change Type | Rollback Approach |
|-------------|-------------------|
| ADD COLUMN (nullable) | DROP COLUMN |
| ADD COLUMN (not null) | Restore from backup or dual-write |
| DROP COLUMN | Restore from backup (data loss!) |
| ADD INDEX | DROP INDEX |
| MODIFY TYPE (widening) | No action needed |
| MODIFY TYPE (narrowing) | Restore from backup |
| ADD FK | DROP FK |
| DROP FK | Re-add FK (verify data integrity) |
1. **Create Migration Script**
- Include UP and DOWN methods
- Add checkpoints for large migrations
- Include progress logging
**Completion criteria:**
- [ ] `pattern_selected` - Migration pattern chosen
- [ ] `rollback_designed` - Rollback procedure documented
- [ ] `script_created` - Migration script with UP/DOWN
### Phase 3: Prepare
**Set up for safe execution:**
See `validation-procedures.md` for integrity checks.
1. **Create Backup**
- Full table backup for destructive changes
- Point-in-time backup for data migrations
- Verify backup is restorable
2. **Set Up Monitoring**
- Query for lock monitoring
- Replication lag tracking
- Error rate alerting
- Progress tracking query
3. **Run Pre-Migration Validation**
```sql
-- Example validation queries
-- Verify row count
SELECT COUNT(*) as pre_count FROM target_table;
-- Verify data integrity
SELECT COUNT(*) as orphans
FROM child_table c
LEFT JOIN parent_table p ON c.parent_id = p.id
WHERE p.id IS NULL;
-- Verify constraints
SELECT constraint_name, constraint_type
FROM information_schema.table_constraints
WHERE table_name = 'target_table';
```
1. **Test Rollback**
- Execute rollback in staging
- Verify data is preserved
- Measure rollback duration
**Completion criteria:**
- [ ] `backup_created` - Backup verified restorable
- [ ] `monitoring_active` - Dashboards and alerts ready
- [ ] `pre_validation_passed` - All integrity checks green
- [ ] `rollback_tested` - Rollback verified in staging
### Phase 4: Execute
**Run the migration:**
See `large-scale-migration.md` for batch processing.
1. **Announce Migration**
- Notify stakeholders
- Post in incident channel
- Update status page if needed
2. **Execute with Monitoring**
For batched migrations:
```sql
-- Example batch processing
DO $$
DECLARE
batch_size INT := 10000;
total_rows INT;
processed INT := 0;
BEGIN
SELECT COUNT(*) INTO total_rows FROM target_table WHERE condition;
WHILE processed < total_rows LOOP
UPDATE target_table
SET new_column = transform(old_column)
WHERE id IN (
SELECT id FROM target_table
WHERE condition AND new_column IS NULL
LIMIT batch_size
);
processed := processed + batch_size;
RAISE NOTICE 'Processed % of % rows', processed, total_rows;
-- Brief pause to reduce lock contention
PERFORM pg_sleep(0.1);
END LOOP;
END $$;
```
1. **Monitor During Execution**
- Watch replication lag
- Monitor lock waits
- Track error rates
- Check application health
2. **Abort Criteria**
- Replication lag > 30 seconds
- Lock wait > 60 seconds
- Error rate spike > 5%
- Application errors increasing
**Completion criteria:**
- [ ] `migration_executed` - All changes applied
- [ ] `no_abort_triggered` - Execution completed without abort
- [ ] `stakeholders_notified` - Team informed of completion
### Phase 5: Verify
**Confirm migration success:**
1. **Run Post-Migration Validation**
```sql
-- Verify row count matches expectation
SELECT COUNT(*) as post_count FROM target_table;
-- Verify data transformation
SELECT COUNT(*) as failed_transforms
FROM target_table
WHERE new_column IS NULL AND old_column IS NOT NULL;
-- Verify referential integrity
SELECT COUNT(*) as broken_refs
FROM child_table c
LEFT JOIN parent_table p ON c.parent_id = p.id
WHERE p.id IS NULL;
```
1. **Application Health Check**
- Run smoke tests
- Verify critical paths work
- Check error rates normalized
2. **Compare Pre/Post Metrics**
- Row counts match expectations
- Query performance acceptable
- No data loss detected
**Completion criteria:**
- [ ] `post_validation_passed` - All integrity checks green
- [ ] `application_healthy` - Critical paths working
- [ ] `metrics_verified` - Pre/post comparison acceptable
### Phase 6: Document
**The migration is NOT complete until documented:**
1. **Update Changelog**
- Note the migration
- Document any data transformations
- Record rollback procedure used
2. **Update Schema Documentation**
- Update ERD if applicable
- Update data dictionary
- Note any deprecated columns
3. **Close Migration Ticket**
- Link to monitoring during execution
- Document any issues encountered
- Record actual vs estimated duration
4. **Schedule Cleanup (if needed)**
- For Expand-Contract: Plan contraction phase
- For Shadow Table: Plan old table removal
- Set reminder for cleanup deadline
**Completion criteria:**
- [ ] `changelog_updated` - Migration documented
- [ ] `schema_docs_updated` - Documentation current
- [ ] `ticket_closed` - Migration ticket resolved
- [ ] `cleanup_scheduled` - Follow-up tasks created
## Red Flags - STOP and Follow Process
If you catch yourself thinking:
- "Just run the migration, we can fix issues later"
- "It's only adding a column, no need to plan"
- "We don't have time for a rollback plan"
- "The table is small enough, skip batching"
- "We can restore from backup if needed" (without testing)
- "The migration ran fine in staging"
- "Let's do it during low traffic, should be fine"
- "Skip validation, we trust the transformation"
**ALL of these mean: STOP. Return to Phase 2.**
## Common Rationalizations
| Excuse | Reality |
|--------|---------|
| "It's just a nullable column" | Nullable columns become NOT NULL. Plan for it. |
| "Table has only 100K rows" | Tables grow. Build habits for when it's 100M. |
| "Staging worked fine" | Production has different data, scale, and traffic patterns. |
| "We can restore from backup" | Backup restore = downtime. Test it, measure it. |
| "It's off-peak hours" | Off-peak is when batch jobs run. Verify traffic patterns. |
| "Migration tool handles rollback" | Tools generate rollback, not verify it. Test manually. |
| "We've done this before" | Past success doesn't guarantee future success. Follow process. |
| "Business is pressuring us" | Outages cost more than delays. Process protects everyone. |
## Quick Reference
| Phase | Key Activities | Verification Key |
|-------|---------------|------------------|
| **1. Assess** | Type, impact, risk level | `risk_level_classified` |
| **2. Plan** | Pattern, rollback, script | `rollback_designed` |
| **3. Prepare** | Backup, monitoring, test rollback | `rollback_tested` |
| **4. Execute** | Announce, batch, monitor | `migration_executed` |
| **5. Verify** | Validation, health, metrics | `post_validation_passed` |
| **6. Document** | Changelog, schema docs, cleanup | `ticket_closed` |
## Risk-Based Response Times
| Risk Level | Max Duration | Rollback Window | Required Approvals |
|------------|--------------|-----------------|-------------------|
| **Low** | 1 hour | 24 hours | 1 reviewer |
| **Medium** | 4 hours | 72 hours | 2 reviewers |
| **High** | 1 day | 1 week | Tech lead + DBA |
| **Critical** | 1 week | 2 weeks | Architecture review |
## CI/CD Integration
Database migrations require careful coordination with deployment pipelines.
### Environment Progression
**Always progress: Dev → Staging → Production**
| Environment | Purpose | Migration Timing | Approval |
|-------------|---------|------------------|----------|
| **Dev** | Experiment freely | On commit | None |
| **Staging** | Verify with prod-like data | Pre-deploy | Auto |
| **Production** | Real execution | During deploy window | Manual |
**Key principle:** Migrations that pass staging with production-like data volume succeed in production.
### Pipeline Integration Patterns
**1. Pre-Deploy Migration (Recommended)**
```yaml
# CI/CD pipeline example
stages:
- test
- migrate-staging
- validate-staging
- approve-production
- migrate-production
- deploy-application
- validate-production
migrate-production:
script:
- ./run-migration.sh --env production
- ./validate-migration.sh --env production
when: manual # Require explicit approval
allow_failure: false
```
**2. Application-Driven Migration (ORM Tools)**
```yaml
# For ORM-managed migrations (Prisma, TypeORM, Django, Rails)
deploy-production:
script:
# Backup before ORM migration
- ./backup-database.sh
# Run ORM migration with timeout
- timeout 30m npx prisma migrate deploy
# Validate after migration
- ./validate-schema.sh
on_failure:
- ./alert-oncall.sh "Migration failed"
```
### ORM Migration Tool Guidelines
| Tool | Migration Command | Rollback Command | Notes |
|------|-------------------|------------------|-------|
| **Prisma** | `prisma migrate deploy` | Manual or `prisma migrate reset` | No auto-rollback in prod |
| **TypeORM** | `typeorm migration:run` | `typeorm migration:revert` | Revert runs DOWN method |
| **Django** | `python manage.py migrate` | `python manage.py migrate app 00XX` | Specify target migration |
| **Rails** | `rails db:migrate` | `rails db:rollback STEP=1` | STEP controls rollback depth |
| **Flyway** | `flyway migrate` | `flyway undo` (Teams only) | Undo requires paid version |
| **Liquibase** | `liquibase update` | `liquibase rollback` | Requires rollback tags |
**ORM Best Practices:**
- Always generate DOWN migration even if ORM doesn't require it
- Test ORM-generated SQL before production (use `--dry-run` or `--preview`)
- Set migration timeout (ORM defaults are often too generous)
- Capture migration output for audit trail
### Deployment Window Coordination
```dot
digraph deployment_window {
rankdir=LR;
node [shape=box];
"Announce Window" -> "Run Pre-checks";
"Run Pre-checks" -> "Execute Migration";
"Execute Migration" -> "Verify Success";
"Verify Success" -> "Deploy App" [label="pass"];
"Verify Success" -> "Rollback" [label="fail"];
"Deploy App" -> "Close Window";
"Rollback" -> "Close Window";
}
```
**Checklist for deployment windows:**
- [ ] Stakeholders notified 24h in advance
- [ ] On-call DBA available during window
- [ ] Rollback script tested and ready
- [ ] Monitoring dashboards open
- [ ] Status page updated to "Maintenance"
### Environment-Specific Configuration
```yaml
# Example: environment-specific migration config
migration:
dev:
batch_size: 50000 # Faster iteration
pause_between: 10ms
timeout: 10m
require_rollback_test: false
staging:
batch_size: 10000 # Match production settings
pause_between: 100ms
timeout: 30m
require_rollback_test: true
production:
batch_size: 5000 # Conservative
pause_between: 200ms
timeout: 60m
require_rollback_test: true
require_manual_approval: true
```
## Supporting Files
These files provide detailed guidance for specific phases:
- **`expand-contract-patterns.md`** - Zero-downtime migration techniques
- **`large-scale-migration.md`** - Batch processing, lock minimization, progress tracking
- **`rollback-strategies.md`** - Rollback procedures by migration type
- **`validation-procedures.md`** - Pre and post-migration integrity checks
## Related Skills
- **superpowers:systematic-debugging** - For diagnosing migration failures
- **superpowers:incident-response** - If migration causes production incident
- **superpowers:test-driven-development** - For testing data transformations
## Related Agents
- **data-engineer** - For schema design and query optimization context
- **migration-specialist** - For legacy system modernization context
## Real-World Impact
From database migration data:
- Systematic migrations: 98% success rate, avg 2 hours total
- Ad-hoc migrations: 70% success rate, avg 8 hours (including rollbacks)
- Pre-tested rollback: 95% successful recovery in <15 minutes
- Untested rollback: 40% require restore from backup (hours of downtime)