Autotask project structure - projects, phases, tasks, and milestones - including project and task fields, status values, resource assignment, and how project work links to contract billing for MSP project managers.
Scanned 9/5/2026
Install to Claude Code
npx -y skills add WYRE-AI/msp-claude-plugins --skill projects --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Projects?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/wyre-ai-projects-msp-claude-plugins)More formats (shields.io, HTML) on the badges page.
---
name: "Autotask Projects"
description: >
Autotask project structure - projects, phases, tasks, and milestones - including project
and task fields, status values, resource assignment, and how project work links to
contract billing for MSP project managers.
when_to_use: >-
When creating projects, managing tasks, phases, milestones, or resource assignments in
Autotask. Use when: autotask project, autotask task, project management, project phase,
project milestone, resource assignment, project billing, or project timeline.
---
# Autotask Projects Management
## Overview
Autotask Projects extend beyond simple ticketing to handle structured work with defined phases, tasks, dependencies, and resource assignments. Projects are used for implementations, migrations, onboarding, and any work requiring planning and tracking.
## Anti-triggers
- **Reactive service desk work** — a project Task and a Ticket are
different entities with different tools (`autotask_create_task` vs
`autotask_create_ticket`); use `autotask-tickets`.
- **Scheduling a technician's visit** — booked onsite blocks are
service calls; use `autotask-service-calls`.
- **Hours logged against project tasks** — use `autotask-time-entries`.
## Key Concepts
### Project Structure
```
Project
├── Phase 1
│ ├── Task 1.1
│ ├── Task 1.2
│ └── Milestone: Phase 1 Complete
├── Phase 2
│ ├── Task 2.1
│ ├── Task 2.2
│ └── Milestone: Phase 2 Complete
└── Final Milestone: Project Complete
```
### Project Fields
| Field | Description | Required |
|-------|-------------|----------|
| `id` | Unique identifier | System |
| `projectName` | Project name | Yes |
| `companyID` | Client company | Yes |
| `projectType` | Type category | Yes |
| `status` | Project status | Yes |
| `startDate` | Planned start | No |
| `endDate` | Planned end | No |
| `projectLeadResourceID` | Project manager | No |
| `department` | Department | No |
| `estimatedRevenue` | Expected revenue | No |
| `contractID` | Associated contract | No |
### Project Status Values
| ID | Status | Description |
|----|--------|-------------|
| 1 | New | Just created |
| 5 | Active | In progress |
| 8 | On Hold | Temporarily paused |
| 10 | Complete | Finished |
| 12 | Cancelled | Terminated |
### Task Fields
| Field | Description | Required |
|-------|-------------|----------|
| `id` | Unique identifier | System |
| `projectID` | Parent project | Yes |
| `phaseID` | Parent phase | No |
| `taskName` | Task title | Yes |
| `status` | Task status | Yes |
| `assignedResourceID` | Assigned tech | No |
| `estimatedHours` | Estimated effort | No |
| `startDate` | Task start | No |
| `endDate` | Task due date | No |
| `priority` | Task priority | No |
## API Patterns
### Creating a Project
```http
POST /v1.0/Projects
Content-Type: application/json
```
```json
{
"projectName": "Acme Corp - Office 365 Migration",
"companyID": 12345,
"projectType": 1,
"status": 1,
"startDate": "2024-03-01",
"endDate": "2024-04-15",
"projectLeadResourceID": 29744150,
"description": "Migrate from on-prem Exchange to Office 365",
"estimatedRevenue": 15000.00,
"contractID": 54321
}
```
### Creating a Phase
```http
POST /v1.0/Phases
Content-Type: application/json
```
```json
{
"projectID": 98765,
"title": "Phase 1: Planning & Assessment",
"description": "Initial assessment and migration planning",
"startDate": "2024-03-01",
"dueDate": "2024-03-08",
"estimatedHours": 16
}
```
### Creating a Task
```http
POST /v1.0/ProjectTasks
Content-Type: application/json
```
```json
{
"projectID": 98765,
"phaseID": 11111,
"taskName": "Document current Exchange environment",
"status": 1,
"assignedResourceID": 29744150,
"estimatedHours": 4,
"startDate": "2024-03-01",
"endDate": "2024-03-02",
"priority": 2
}
```
### Searching Projects
**Active projects for a company:**
```json
{
"filter": [
{"field": "companyID", "op": "eq", "value": 12345},
{"field": "status", "op": "eq", "value": 5}
]
}
```
**Projects by lead:**
```json
{
"filter": [
{"field": "projectLeadResourceID", "op": "eq", "value": 29744150},
{"field": "status", "op": "in", "value": [1, 5]}
]
}
```
### Creating Time Entry on Task
```http
POST /v1.0/TimeEntries
Content-Type: application/json
```
```json
{
"taskID": 22222,
"resourceID": 29744150,
"dateWorked": "2024-03-01",
"startDateTime": "2024-03-01T09:00:00Z",
"endDateTime": "2024-03-01T12:00:00Z",
"hoursWorked": 3,
"summaryNotes": "Documented Exchange server configuration",
"billingCodeID": 29683556
}
```
### Updating Project Status
```http
PATCH /v1.0/Projects
Content-Type: application/json
```
```json
{
"id": 98765,
"status": 5,
"actualStartDate": "2024-03-01"
}
```
## Common Workflows
### Project Setup
1. **Create project**
- Link to company and contract
- Set project lead
- Define timeline
2. **Create phases**
- Logical groupings of work
- Sequential ordering
3. **Create tasks**
- Assign to phases
- Estimate hours
- Set dependencies
4. **Assign resources**
- Assign tasks to techs
- Balance workload
### Project Execution
1. **Start project** - Update status to Active
2. **Work tasks** - Log time entries
3. **Complete tasks** - Update task status
4. **Track progress** - Monitor vs estimates
5. **Complete phases** - Mark milestones
6. **Close project** - Final status update
### Project Billing
Projects can be billed:
- **Fixed Fee** - Set project price
- **Time & Materials** - Bill actual time
- **Against Contract** - Deduct from prepaid hours
Always associate project with contract for proper billing flow.
## Error Handling
### Common API Errors
| Code | Message | Resolution |
|------|---------|------------|
| 400 | Invalid projectType | Use valid project type ID |
| 400 | EndDate before StartDate | Fix date sequence |
| 404 | Project not found | Verify project ID |
| 409 | Cannot delete - has time entries | Archive instead of delete |
### Validation Errors
**"ProjectName is required"** - Project name cannot be empty
**"Invalid companyID"** - Company must exist and be active
**"PhaseID does not belong to Project"** - Task's phase must be in same project
## Best Practices
1. **Use phases** - Organize work logically
2. **Estimate accurately** - Track estimates vs actuals
3. **Assign tasks** - Don't leave tasks unassigned
4. **Update status** - Keep project status current
5. **Link to contracts** - Ensure billing flows correctly
6. **Document milestones** - Define clear completion criteria
7. **Regular reviews** - Weekly project status checks
## Related Skills
- [Autotask Tickets](../tickets/SKILL.md) - Ad-hoc service work
- [Autotask Contracts](../contracts/SKILL.md) - Project billing
- [Autotask CRM](../crm/SKILL.md) - Company relationships