Turn a plan or set of milestones into a timeline / Gantt chart. Use when asked to build a roadmap, schedule phases, show a project timeline, or visualize what happens when. Produces a ready-to-render Mermaid Gantt chart (renders live, exportable as PNG/SVG) — and, because it has real dates, the result also exports to a calendar (.ics) — plus notes on the critical path and risks.
Scanned 9/3/2026
Install to Claude Code
npx -y skills add mohitagw15856/pm-claude-skills --skill gantt-roadmap --agent claude-codeInstalls into .claude/skills of the current project.
Are you the author of Gantt Roadmap?
Add the live security badge to your README — it updates automatically with every re-scan.
[](https://www.skillsdirectory.com/skills/mohitagw15856-gantt-roadmap)More formats (shields.io, HTML) on the badges page.
---
name: gantt-roadmap
description: "Turn a plan or set of milestones into a timeline / Gantt chart. Use when asked to build a roadmap, schedule phases, show a project timeline, or visualize what happens when. Produces a ready-to-render Mermaid Gantt chart (renders live, exportable as PNG/SVG) — and, because it has real dates, the result also exports to a calendar (.ics) — plus notes on the critical path and risks."
homepage: https://mohitagw15856.github.io/pm-claude-skills/skill/gantt-roadmap.html
metadata:
{
"openclaw": { "emoji": "🖼" }
}
---
# Gantt / Roadmap Skill
A list of tasks doesn't show what runs in parallel, what blocks what, or where the crunch is. A Gantt chart
does. This skill turns a plan into a **Mermaid Gantt chart** with phases (sections), dated tasks, dependencies,
and milestones — a real schedule, not a wish list. Because the output carries real dates, the playground can
also export it straight to a calendar (`.ics`).
## Required Inputs
Ask for these only if they aren't already provided:
- **The work** — phases and tasks to schedule.
- **Timing** — a start date, and durations or end dates (or relative ordering you can date from the start).
- **Dependencies** — what must finish before what can start.
- **Milestones** — the dated checkpoints (kickoff, beta, GA, launch).
If exact dates aren't given, anchor to a start date and lay tasks out by stated duration/order; flag the dates as planning estimates.
## Output Format
### [Project] — roadmap
One line on the time span and goal.
```mermaid
gantt
title [Project] roadmap
dateFormat YYYY-MM-DD
axisFormat %b %d
section Discovery
Research :done, r1, 2026-07-01, 10d
Spec sign-off :milestone, m1, 2026-07-15, 0d
section Build
Core build :active, b1, after m1, 20d
Integrations : b2, after b1, 10d
section Launch
Beta :milestone, m2, 2026-08-25, 0d
GA :milestone, m3, 2026-09-10, 0d
```
**Critical path** — the chain of dependent tasks that sets the end date.
**Risks / buffers** — where the schedule is tight, what could slip, where buffer exists.
**Assumptions** — any dates you estimated rather than were given.
## Mermaid Rules (so it renders)
- Start with `gantt`, then `title`, `dateFormat YYYY-MM-DD`, optional `axisFormat`.
- Group with `section Name`. Task line: `Label : [status,] id, start, duration` (e.g. `:active, b1, 2026-07-01, 20d`).
- Dependencies use `after <id>` as the start. Milestones use the `milestone` tag with `0d`.
- Use real ISO dates (`YYYY-MM-DD`) so the calendar (.ics) export works.
## Quality Checks
- [ ] Tasks are grouped into phases (sections) and have real start dates/durations
- [ ] Dependencies use `after` so the schedule reflects what blocks what
- [ ] Milestones are marked as milestones, not full-width bars
- [ ] The critical path is identified, with risks/buffers noted
- [ ] The Mermaid block renders, and dates are ISO so .ics export works
## Anti-Patterns
- [ ] Do not list tasks with no dates or durations — that's a checklist, not a timeline
- [ ] Do not ignore dependencies — overlapping things that can't overlap is a fake plan
- [ ] Do not draw milestones as long bars — they're points in time
- [ ] Do not use ambiguous date formats — stick to `YYYY-MM-DD`
- [ ] Do not present estimated dates as commitments — flag assumptions
## Based On
Project scheduling (Gantt charts, critical path, milestones, dependencies), expressed as renderable Mermaid.
Is this your skill, or is something wrong with this listing? Request removal or report an issue. Author removals are honored within 72 hours.
No comments yet. Be the first to comment!